a. Ohlson Landscaping (1949 Atlantic Street) (north of Frost Avenue)
1. Conditional Use Permit (Metal Building)
2. Conditional Use Permit (Outdoor Storage)
7. Unfinished Business
None
8. Visitor Presentations
10.
9. Commission Presentations
a. January 27 Council Meeting: Mr. Rossbach
b. February 10 Council Meeting: Ms. Fischer
c. February 24 Council Meeting: Mr. Pearson
Staff Presentations
a. Reschedule February 17 Meeting (President's Day) - Wednesday, February 197
11. Adjournment
WELCOME TO THIS MEETING OF THE
PLANNING COMMISSION
This outline has been prepared to help you understand the public meeting process.
The review of an item usually takes the following form:
The chairperson of the meeting will announce the item to be reviewed and
ask for the staff report on the subject.
Staff presents their report on the matter.
The Commission will then ask City staff questions about the proposal.
The chairperson will then ask the audience if there is anyone present who wishes to
comment on the proposal.
This is the time for the public to make comments or ask questions about the proposal.
Please step up to the podium, speak clearly, first giving your name and address and
then your comments.
After everyone in the audience wishing to speak has given his or her comments, the
chairperson will close the public discussion portion of the meeting.
The commission will then discuss th'e proposal. No further public comments are
allowed.
The Commission will then make its recommendation or decision.
All decisions by the Planning Commission are recommendations to the City Council.
The City Council makes the final decision.
jw/pc\pcagd
Revised: 01/95
DRAFT
MINUTES OF THE MAPLEWOOD PLANNING COMMISSION
1830 COUNTY ROAD B EAST, MAPLEWOOD, MINNESOTA
WEDNESDAY, JANUARY 22, 2003
I. CALL TO ORDER
Chairperson Fischer called the meeting to order at 7:00 p.m.
I1. ROLL CALL
Commissioner Tushar Desai Present
Commissioner Mary Dierich Present
Commissioner Lorraine Fischer Present
Commissioner Matt Ledvina Absent
Commissioner Jackie Monahan-Junek Absent
Commissioner Paul Mueller Present
Commissioner Gary Pearson Present
Commissioner William Rossbach Present
Commissioner Dale Trippler Present
Staff Present:
Chris Cavett, Assistant City Engineer
Ken Roberts, Associate Planner
Lisa Kroll, Recording Secretary
III. APPROVAL OF AGENDA
Commissioner Pearson moved to approve the agenda.
Commissioner Desai seconded.
Ayes- Desai, Dierich, Fischer, Mueller,
Pearson, Rossbach, Trippler
The motion passed.
IV. APPROVAL OF MINUTES
Approval of the planning commission minutes for January 6, 2003.
Chairperson Fischer had a correction at the top of page 2 Nays should be changed to
Abstentions.
Commissioner Trippler moved to approve the planning commission minutes for January 6, 2003
with the changes.
Commissioner Dierich seconded.
Ayes- Desai, Dierich, Fischer, Mueller,
Pearson, Rossbach, Trippler
The motion passed.
-r
Planning Commission
Minutes of 01-22-03
-2-
V. PUBLIC HEARING
a. Highwood Farm (Town houses) - Highwood Avenue
Mr. Roberts said Mr. Charles Cox is proposing to build 18 town houses (in three six-unit buildings)
in a development called Highwood Farm. It would be on a 3.71-acre site on the south side of
Highwood Avenue, east of Dennis Street. A homeowners association would own and maintain
the common areas.
To build this project, Mr. Cox is requesting that the city approve:
1. A change to the comprehensive plan. This would be from R-1 (single dwellings) to R-3(M)
(medium density residential) for the site.
2. A conditional use permit (CUP) for a planned unit development (PUD): This PUD will give the
city and developer a chance to be more flexible with site design and development details (such
as setbacks and street right-of-way and pavement widths) than the standard city requirements
would normally allow. Specifically, this PUD will allow the town houses and a driveway to have
a smaller setback to the side property lines than code usually allows and to have the town
houses on a private driveway.
3. A preliminary plat to create the 19 lots in the development (18 lots for the town houses and one
lot for the common area).
Mr. Roberts said the applicant has not yet applied for design approval for this project. If the city
approves the requests, then the applicant will apply to the city for final plat approval and design
approval (including architectural and landscape plans).
The 18 units on the 3.71-acre site means there would be 4.86 units per gross acre which is
consistent with the density standards set in the Maplewood Comprehensive Plan for medium-
density residential development (of up to six units per gross acre). In addition, the proposed
development density would be consistent with the density standards recommended by the
Metropolitan Council for housing in first-ring suburbs. For a comparison, the comprehensive plan
allows developments with single dwellings to have up to 4.1 units per gross acre. As such, on a
3.71-acre site, there could be up to 15 single-family homes.
The applicant has applied for a conditional use permit (CUP) for a planned unit development
(PUD) for the 18-unit housing development. In addition, having a PUD gives the city and
developer a chance to be more flexible with site design and development details than the
standard city requirements would normally allow. In this case, the developer is requesting the
CUP for the PUD because the proposed side yard setbacks for the buildings and for the driveway
do not meet the usual city setback standards.
Mr. Roberts said specifically, the driveway on the east side of the site would be 12 feet from the
side property line (instead of the usual 20 feet) and the town houses would be 47 feet from the
west property line (instead of the usual 50 feet).
Planning Commission
Minutes of 01-22-03
-3-
Mr. Roberts said the proposed setback deviations would not constitute a threat to the property
values, safety, health or general welfare of the owners or occupants of nearby land and are
required for reasonable and practicable physical development and are not required solely for
financial reasons. However, in consideration for the PUD, the city should require the developer to
record a conservation easement over the undisturbed area and to construct the development with
a high level of architectural design and landscaping elements, including the size and quantities of
materials.
Mr. Roberts said Mr. Cox has designed this development as a common interest community (CIC)
with three proposed buildings platted as one lot each. The buildings will then be divided into
separate units, with the prospective buyers owning from wall to wall, as opposed to owning the
land that a town house sits on and a small portion of the land surrounding it. If approved, the
developer will be forming a homeowners association with documents (declarations) specifying the
legal responsibility of the association and homeowners for maintenance of the units and common
grounds.
Mr. Roberts said data from the Institute of Traffic Engineers (ITE) says thatl on average, a town
house will generate seven vehicle trips per day and that a single dwelling will generate about ten
vehicle.trips per day. As such, 18 town houses would create about 126 vehicle trips from the site
while 10 single dwellings would create about 100 vehicle trips from the site.
Mr. Roberts said Lieutenant Banick of the Maplewood Police Department provided staff with
comments about this proposal and the first proposal that had 10 lots for the site. The main
concern expressed by Lt. Banick With the development of this site is the increase in calls for
service in the south end of the city. As south Maplewood has grown and developed, there has
been an increase in the calls to the police department from the part of the city. He also noted
"every development throughout the city has a tendency to increase police calls for service." Lt.
Banick also stated that last summer the police department received several traffic and speeding
complaints from residents on Highwood Avenue. As such, he asked what the impact would be on
current residents with the increasing traffic? Because of these concerns, he recommends that the
city limit the growth in this area by restricting this development to ten residential units.
Commissioner Pearson asked staff if there was a maximum traffic count for that area?
Mr. Cavett, Assistant City Engineer, said as an example, the 2001 traffic counts were 2,450
vehicles per day on Highwood Avenue and 2,600 vehicles per day on Century Avenue. A traffic
comparison in that area for McKnight Road totaled 4,900 vehicles per day between Highwood
Avenue and Linwood Avenue.
Commissioner Dierich asked staff why this road would not be a public road?
Mr. Cavett said this is a private road because it doesn't meet the right of way requirements that
are necessary on a public road. The homeowners association will be maintaining the driveways
and sidewalks. It would also require a cul-de-sac rather than the hammerhead turnaround,
requiring more grading and tree removal.
Planning Commission
Minutes of 01-22-03
-4-
Commissioner Pearson asked staff if the project went forward with 20 foot roadways and there
was no parking on the road and it is a private driveway, does the police department have the
authority to ticket or tow for parking violations or is that up to the homeowners association to
police?
Mr. Roberts said the police department cannot tow vehicles from private property. As far as
ticketing authority for the police department he is not sure. He believes the Fire Marshal has the
authority to ticket vehicles because of the 20 foot width standard for life safety.
Commissioner Desai asked if staff could clarify where there would be additional parking on the
site?
Mr. Roberts displayed the map to show where additional parking would be allowed on the site.
Commissioner Mueller asked how many stories these townhomes would have?
Mr. Roberts said he believes they would be two story townhomes that are 25 feet by 50 feet with
underground parking.
Commissioner Dierich asked if the city made this a public drive would it meet the city's criteria and
if not what would it need to meet the requirements besides a turn around?
Mr. Cavett said it would need a minimum 24-foot width, a right of way of 50 feet, a minimum 90-
foot wide cul-de-sac and the setbacks would change for the buildings.
Commissioner Mueller asked how much the townhomes would sell for?
Mr. Roberts said they would sell for between $300,000 to $350,000.
Commissioner Mueller said he thought the city was concerned about affordable housing and in
his opinion this is an expensive home.
The applicant, Mr. Charles Cox, 1111 McKnight Road South, Maplewood, addressed the
commission. He said at this time he has no concerns about the staff conditions and has no
questions for the commission.
Commissioner Mueller asked Mr. Cox how many stories the townhomes would have?
Mr. Cox said the townhomes would be two stories and the middle unit would have the ability to
have a loft. He said they will have three bedrooms and the price will be around $300,000.
Commissioner Dierich commented the applicant had done a good job of listening to what the
neighbors and the city had to say regarding this proposal. She feels Mr. Cox tried to do
something that was more sensitive to the land compared to the last proposal.
Commissioner Trippler asked Mr. Cox to elaborate on the property to the south of thr
development? Are there any plans to have a walkway or recreational area on the property?
Planning Commission
Minutes of 01-22-03
-5-
Mr. Cox said there are no plans for the property to the south at this time. He said they have
looked at several different options for the land and have also looked at gifting the land to the
community. They will take the Walkway or recreational area ideas into consideration. They are
still in the design stage and have quite a ways to go until they get to that point.
commissioner Trippler said because of the noise potential from Highway 494 has he thought
about noise barriers on the south property to help mitigate the noise?
Mr. Cox said staff recommended a noise study. If it's determined that the noise exceeds the
noise standards they will take staff's recommendation into consideration.
Commissioner Desai said he has a concern about additional parking. For a townhome costing
$300,000 he expects more than two spaces for parking. Visitors will be coming to these people's
homes and he perceives a problem with the neighbors regarding the parking.
Mr. David Myers of CEC Development, addressed the commission. Mr. Myers said there are two
parking spots plus a guest parking spot for each townhome with the proposed underground
parking.
Commissioner Rossbach said he is pleased that the commission is looking at cluster housing. He
does have a concern that when ever the city is looking at a PUD, the density goes up. He does
not think that is part of a PUD that was put into the ordinance. His thought is this proposal ended
up with :18 units. This was a piece of property that supported 15 units with the current R-1 land
use designation. When the city started 'out with a proposed plan that had 10 houses and the
suggestion was to save more of this land he did not think this proposal would come close to
almost doubling the amount of homes on this property. He wonders Why this proposal is going
from 10 single-family homes to 18 townhomes. The density does not need to be changed
because the Met Council has already approved the city's comprehensive plan. He thinks the
PUD should be required, leave it zoned as R-1 and have 15 townhome units.
Mr. Myers said in the city's current R-1 plan it allows them to put in 16.1 homes on this property
based on the number of square feet. But because of the way it was set-up before they couldn't
put 16 homes on the property comfortably. The reason they put the underground parking in was
because it gave them additional credit towards the amount of units they could put on the land.
Commissioner Rossbach said the credits don't mean anything in a PUD because they don't apply
this is what a PUD does.
Mr. Myers said the original R-1 would have allowed them to put 16.1 homes on the property.
Commissioner Rossbach asked staff if that number was correct because that wasn't the number
in the staff report.
Mr. Roberts said he was not clear where Mr. Myers came up with those numbers.
Mr. Myers said when he read the Maplewood Zoning Ordinance it said there are 43,520 square
feet in an acre. Multiply that number by 3.71 and divide it by 10,000 square feet that equals 16.1
houses. He said it was all explained in the letter he wrote on page 18 of the staff report,
Planning Commission
Minutes of 01-22-03
-6-
Mr. Roberts said he thinks the confusion is from looking at the density standards in the
comprehensive plan verses minimal lot standards that are in the zoning code. Those numbers
don't necessary line up with each other. The density standards are set by the comprehensive
plan and that is where it says up to 6 units per gross acre is medium density. The 10,000 square
foot minimum that Mr. Myers is referring to is the minimum lot size in the R-1 zoning standard.
That density standard works in theory but doesn't account for any public right of way or streets
that would be necessary to serve as access.
Commissioner Dierich said she agrees with Mr. Rossbach and in fact if the Met Council said the
maximum is 3 homes per acre she would feel more comfortable with their decision. She let staff
know that she could live with 12 homes but would be more comfortable with 10 homes even
though she thinks this is a much stronger plan.
Chairperson Fischer said she believes the Met Council's decision was a minimum of 3 homes per
acre rather than a maximum of 3 homes per acre.
Commissioner Dierich said she thinks this is a far stronger development if the applicant pulled the
middle unit out so the trees would be conserved, slide the two units sideways 90 degrees, then
you would meet the setbacks and you would have a nice buffer between the two units. She is
concerned about the narrowness between the private driveway and the neighbors yard as well the
12-foot strip of land. The normal setback is 20 feet and this seems unfair to have a setback of 12
feet. If the city was able to reconfigure the plan on page 14 item 8 b. of the staff report and it was
approved by the city council, she would vote for the Iow density. She would recommend deleting
the last part of that line that says "unless approved by the city council".
Commissioner Rossbach said every time the city is reviewing a PUD the density is exceeded. He
said it is not just this development it is every time a PUD is being reviewed. He said the applicant
could have put 15 units in but instead he chose to put in 18 units. He said he does not want to
change the rules just work within the rules.
Commissioner Trippler said he is not quite sure how someone would pay $300,000 for a 25 foot
by 50-foot townhome.
Mr. Cox said he wants to remind planning commission members not to make a decision based on
the price of these townhomes or to base their decision on the profit that the developer will make
on this project.
Commissioner Rossbach moved to deny the resolution on page 30 of the staff report. This
resolution changes the land use plan for the Highwood Farm plat on the south side of Highwood
Avenue, east of Dennis Street. This change is from R-1 (single dwellings) to R-3 (M) (medium-
density residential.) (Changes are in bold and deletions are bolded and have a strike
through them.) The city is making this change because:
It would be consistent with the goals and objectives of the comprehensive plan. These
include having similar uses fronting on the same street, having a grading plan that
preserves many significant natural features and uses a planned unit development to allo~
for creative design solutions.
Planning Commission
Minutes of 01-22-03
-7-
This site is proper for and consistent with the city's policies for medium-density residential
use. This includes:
a. Creating a transitional land use between the existing Iow-density residential and the
existing telecommunications Site.
b. Being on a collector street and it is near an arterial street.
Commissioner Dierich seconded.
Ayes- Desai, Dierich, Pearson,
Rossbach, Trippler
Nays- Fischer, Mueller
Commissioner Rossbach moved to approve the resolution on page 31 of the staff report. This
resolution approves a conditional use permit for a planned unit development for the Highwood
Farm development on the south side of Highwood Avenue, east of Dennis Street. The city bases
this approval on the findings required by code. Approval is subject to the following conditions:
All construction shall follow the plans approved by the city. The city council may approve
major changes to the plans. The Director of Community Development may approve minor
changes to the plans. Such changes shall include:
a. Revising the grading and site plans to show:
(1) Limit the number of units on the property to 15.
{-1-)- (2) The developer minimizing the loss or removal of natural vegetation.
(3)
All driveways at least 20 feet wide. If the developer wants to have parking
on one side of the main drive (Ferndale Street), then it must be at least 28
feet wide.
(4)
All parking stalls with a width of at least 9.5 feet and a length of at least 18
feet. Revise the plans to reduce the number of spaces between the
buildings from three to two to allow more space between the parking area
and the edge of the building. Also, revise the parking spaces and the turn-
around area at the south end of the site to maximize the number of trees to
be saved and to maximize the number of spaces while minimizing the
amount of hard surface area.
(4)- (5)
Revised storm water pond locations and designs as suggested or required
by the watershed district or city engineer. The ponds shall meet the city's
design standards;
2. The proposed construction must be substantially started within one year of council approval
or the permit shall end. The council may extend this deadline for one year.
Planning Commission
Minutes of 01-22-03
-8-
Have the city engineer approve final construction and engineering plans. These plans shall
meet all the conditions and changes noted in the engineer's memo dated January 14, 2003.
These shall include:
a. Include grading, utility, drainage, erosion control, streets, trails, tree, driveway and
parking lot plans.
Show no grading or ground disturbance in the conservation easement. This land is
to be preserved for open space purposes. The developer and contractors shall
protect this area, including the large trees that are in and near the south side of the
site, from encroachment from equipment, grading or filling.
c. Include a storm water management plan for the proposal.
The design of all ponds shall meet Maplewood's design standards and shall be subject to
the approval of the city engineer. If needed, the developer shall be responsible for getting
any off-site pond and drainage easements.
5. The developer or contractor shall:
a. Complete all grading for the site drainage and the ponds, complete all public
improvements and meet all city requirements.
b. *Place temporary orange safety fencing and signs at the grading limits.
Provide the city with verification that the town houses on the proposed site plan will
meet the state's noise standards. This shall be with a study, testing or other
documentation. If the noise on this site is a factor, then the contractor will have to
build the town houses so that they can meet the noise standards. This may be done
with thicker walls, heavier windows, requiring air conditioning or other sound-
deadening construction methods.
6. The approved setbacks for the principal structures in the Highwood Farm PUD shall be:
a. Front-yard setback (from a public street or a private driveway): minimum - 20 feet,
maximum - 35 feet.
b. Rear- yard setback: 30 feet from any adjacent residential property line.
c. Side-yard setback (town houses): minimum -20 feet from a property line and 20 feet
minimum between buildings.
7. The developer or builder will pay the city Park Access Charges (PAC fees) for each housing
unit at the time of the building permit for each housing unit.
8. Submit the homeowner's association documents to city staff for review and approval.
Planning Commission
Minutes of 01-22-03
-9-
The developer shall provide a permanent means to preserve and maintain the common
open space. This may be done by conservation easement, deed restrictions, covenants or
public dedication. The developer shall record this document with the final plat and before
the city issues a permit for grading or utility construction.
10. The city council shall review this permit in one year.
11.
This approval does not include the design approval for the townhomes. The project design
plans, including architectural, site, lighting, tree and landscaping plans, shall be subject to
review and approval of the community design review board (CDRB). The projects shall be
subject to the following conditions:
a. Meeting all conditions and changes as required by the city council.
b. For the driveways:
(1) Minimum width - 20 feet.
(2) Maximum width - 28 feet.
(3) All driveways less than 28 feet in width shall be posted for "No Parking" on
both sides. Driveways at least 28 feet wide may have parking on one side
and shall be posted for No Parking on one side.
c. Showing all changes required by the city as part of the conditional use permit for the
planned unit development (PUD).
12.
The city shall not issue any building permits for construction on an outlot (per city code
requirements). The developer must record a final plat to create buildable lots in the
preliminary plat before the city will issue a building permit.
Commissioner Rossbach moved to approve the Highwood Farms preliminary plat (received by
the city on December 26, 2002). The developer shall complete the following before the city
council approves the final plat: (Changes are in bold and deletions are bolded and have a
strike through them.)
1. Sign an agreement with the city that guarantees that the developer or contractor will:
Complete all grading for overall site drainage, complete all public improvements
and meet all city requirements.
b. *Place temporary orange safety fencing and signs at the grading limits.
Have Xcel Energy install Group V rate streetlights in two locations - primarily at
the street intersection and near the south end of the driveway. The exact style
and location shall be subject to the city engineer's approval.
Pay the city for the cost of traffic-control, street identification and no parking
signs.
Planning Commission -10-
Minutes of 01-22-03
e. Provide all required and necessary easements, including any off-site easements.
f. Demolish or remove the existing house and garage from the site, and remove all other
buildings, fencing, trailers, scrap metal, debris and junk from the site.
g. Cap and seal all wells on site that the owners are not using; remove septic systems or
drainfields, subject to Minnesota rules and guidelines.
Complete the curb and gutter on Highwood Avenue on the north side of the site. This
is to replace the existing driveways on Highwood Avenue and shall include the
restoration and sodding of the boulevards.
i. Install a sign where the new driveway intersects Highwood Avenue indicating that it is
a private driveway.
Install survey monuments and signs along the edges of the conservation easement
area. These signs shall explain that the area beyond the signs is a conservation
easement area and that there shall be no building, fences, mowing, cutting, filling,
dumping or other ground disturbance in that area. The developer or contractor shall
install these signs before the city issues building permits in this plat.
Have the city engineer approve final construction and engineering plans. The applicant
shall have these plans revised to follow the comments of the city engineer and shall include
the grading, utility, drainage, erosion control, tree and street plans. The plans shall meet
the following conditions:
ao
The erosion control plans shall be consistent with the city code,
The grading plan shall show:
(1)
The proposed building pad elevation and contour information for each
building site. The lot lines on this plan shall follow the approved preliminary
plat.
(2) Contour information for all the land that the construction will disturb.
(3) Building pads that reduce the grading on sites where the developer can
save large trees.
(4) The proposed street and driveway grades as allowed by the city engineer.
(5)
All proposed slopes on the construction plans. The city engineer shall
approve the plans, specifications and management practices for any slopes
steeper than 3:1. One slopes steeper than 3:1, the developer shall prepare
and implement a stabilization and planting plan. At a minimum, the slopes
shall be protected with wood-fiber blanket, be seeded with-a no-
maintenance vegetation and be stabilized before the city approves the fina~
plat.
Planning Commission
Minutes of 01-22-03
-11-
(6)
All retaining walls on the plans. Any retaining walls taller than four feet
require a building permit from the city. The developer shall install a
protective rail or fence on top of any retaining wall that is taller than four
feet.
(7) Sedimentation basins or ponds as required by the watershed board or by
the city engineer.
(8) No grading beyond the plat boundary without temporary grading easements
form the affected property owner(s).
(9) As little grading as possible west and south of the town houses. This is to
keep as many of the existing trees on the site as is reasonably possible.
c. The street, driveway and utility plans shall show:
(1)
The driveway shall be a nine-ton design with a maximum grade of eight
percent and the maximum grade within 75 feet of the intersection at two
percent.
(2)
The street (driveway) with continuous concrete curb and gutter, except where
the city engineer determines that curbing is not necessary for drainage
purposes.
(3)
The removal of the unused driveways and the completion of the curb and
gutter on the south side of Highwood Avenue and the restoration and sodding
of the boulevards.
(4)
The coordination of the water main alignments and sizing with the standards
and requirements of the Saint Paul Regional Water Services (SPRWS). Fire
flow requirements and hydrant locations shall be verified with the Maplewood
Fire Department.
(5)
All utility excavations located within the proposed right-of-ways or within
easements. The developer shall acquire easements for all utilities that would
be outside the project area.
(6) The plan and profiles of the proposed utilities.
(7) A detail of any ponds, the pond outlets and the rainwater gardens. The
contractor shall protect the outlets to prevent erosion.
The drainage plan shall ensure that there is no increase in the rate of storm water
runoff leaving the site above the current (predevelopment) levels. The developer's
· engineer shall:
(1) Verify inlet and pipe capacities.
(2)Submit drainage design calculations.
Planning Commission
Minutes of 01-22-03
-12-
e. *The tree plan shall:
(1) Be approved, along with the landscaping, by the Community Design Review Board
(CDRB) before site grading or final plat approval.
(2) Show where the developer will remove, save or replace large trees. This plan shall
include an inventory of all existing large trees on the site.
(3)
Show the size, species and location of the replacement and screening trees. The
deciduous trees shall be at lest two and one half (2 1,,~) inches in diameter and shall
be a mix of red and white oaks, ash, lindens, sugar maples or other native species.
The coniferous trees shall be at least eight (8) feet tall and shall be a mix of Black
Hills Spruce, Austrian pine and other species.
(4) Show no tree removal in the buffer zones, conservation easement, or beyond the
approved grading and tree limits.
(5) Include for city staff a detailed tree planting plan and material list.
(6)
Group the new news together. These planting areas shall be:
(a) near the ponding areas
(b) on the slopes
(c) along the west side of the site to screen the proposed buildings from
the homes to the west
(7)Show the planting of at least 37 trees after the site grading is done.
3. Change the plat as follows:
a. Redesign the plat to 15 units.
~ b. Add drainage and utility easements as required by the city engineer.
Show drainage and utility easements along all property lines on the final plat.
These easements shall be ten feet wide along the front and rear property
lines and five feet wide along the side property lines.
~ d. Label the common areas as an outlot or as outlots.
d:. e. If allowed, show the conservation easement on the final plat.
f. Showing the building pads and the common area as a Common Interest
Community (CIC).
4. Pay for costs related to the engineering department's review of the construction plans.
Secure and provide all required easements for the development including any off-site
drainage and utility easements. These shall include, but not be limited to, an easement for
the culvert draining the pond at the northwest corner of the plat.
Planning Commission
Minutes of 01-22-03
-13-
o
The developer shall complete all grading for public improvements and overall site drainage.
The city engineer shall include in the developer's agreement any grading that the developer
or contractor has not completed before final plat approval.
Sign a developer's agreement with the city that guarantees that the developer or contractor
will:
a. Complete all grading for overall site drainage, complete all public
improvements and meet all city requirements.
b. *Place temporary orange safety fencing and signs at the grading limits.
Provide for the repair of Highwood Avenue (street, curb and gutter and
boulevard) after the developer connects to the public utilities and builds the
private driveway.
8. Record the following with the final plat:
a. All homeowner's association documents.
A covenant or deed restriction that prohibits any further subdivision or splitting of the
lots or parcels in the plat that would create additional building sites. ~
c. A covenant or deed restriction that prohibits any additional driveways (besides the
one new driveway shown on the project plans) from going onto Highwood Avenue.
d. The conservation easement for the undisturbed area of the site.
The applicant shall submit the language for these dedications and restrictions to the city
for approval before recording. The city will not issue a building permit until after the
developer has recorded the final plat and these documents and covenants.
e
*Submit the homeowners association bylaws and rules to the director of community
development. These are to assure that there will be one responsible party for the
maintenance of the common areas, outlots, private utilities, driveways, retaining walls and
structures.
10. Obtain a permit from the Ramsey-Washington Metro Watershed District for grading.
11.
If the developer decides to final plat part of the preliminary plat, the director of community
development may waive any conditions that do not apply to the final plat.
12.
The developer shall complete all grading for public improvements and overall site drainage.
The city engineer shall include in the developer's agreement any grading that the developer
or contractor has not completed before final plat approval.
*The developer must complete these conditions before the city issues a grading permit or
approves the final plat.
Four open bins for excess landscape material are proposed on the north side of the lot, and two
outdoor enclosed storage bins are proposed on the west side of the lot. In addition, to this extedor
storage, several landscape vehicles and equipment are proposed to be stored outdoors. The storage
of the landscape matedal and outdoor bins require a CUP for exterior storage.
Possible Redevelopment
The building and use of the land is compatible to existing buildings and uses in the area. As an
example, George's Auto Body at 1225 Frost Avenue was approved for a 1,600-square-foot, 25-foot
tall, metal building by the city council in 1988. While a metal building may have been appropriate for
the area in 1988, it may not be appropriate today.
After the COnstruction of the city's first roundabout on the intersection of Frost Avenue and Engli.sh
Street last fall, the city is now considering redevelopment options for the area. While there is no
formal plan for redevelopment, the city should be sensitive to the possible future land uses in the
area while reviewing this proposal, which may include multi-family housing and architecturally
supedor office and retail space. In addition, because there is no formal plan in place for
redevelopment, the city is also bound by the current zoning regulations which allow a metal building
within the Business Commercial zoning distdct with a CUP.
To balance the possible redevelopment with the existing code, staff recommends two changes to the
proposal. First, no extedor storage should be allowed on the site. Extedor storage would not be
compatible to future multi-family housing and the existing single-family housing located to the north of
the property, on the other side of the Gateway Trail. In addition, exterior storage adjacent the
· Gateway Trail woUld be an unsightly proposition. If the applicant requires storage bins for landscape
material, these bins could be stored in the metal building, or a separate structure could be designed
to store this material. Second, some architectural design should be added to the building. Staff
recommends a bdck or stone wainscot be added to at least the north, east, and south sides of the
building, and that four false dormers be added to the roof (similar to dormers recently added to the
Keller Golf Course maintenance building). In addition, earth-tone colors should be used in the metal
panels and roof.
Landscaping/Lighting
The landscape plan includes 18 arborvitaes for the southeast comer of the lot. The COde requires
that only 20 percent of a metal building be visible from the read and adjacent residential property. In
addition, Suzann Willhite, Area Trails and Waterways Supervisor, states in her letter on page 22 that
the Department of Natural Resources has concerns which include the visual quality of the site from
the Gateway Trail. Ms. Willhite recommends native vegetation along the shared property line of the
site and the Gateway Trail to help mitigate the visual impact of a metal building. Also, Chds Cavett,
Assistant CitY Engineer, recommends in his memorandum on pages 23 and 24 the addition of
rainwater gardens and a turf-establishment plan.
For these reasons, additional landscaping will be required to include more substantial evergreen
screening on the southeast side of the lot, native trees and shrubs on the north side of the lot
adjacent the Gateway Trail, rainwater gardens with water tolerant plants, and a turf establishment
plan for the remainder of the green space.
Ohlson Landscaping 2 January 28, 2003
An extedor lighting plan was not submitted with this preposal. City code requires all commereial
developments to submit a photometric lighting plan to ensure that illumination frem exterior lights
does not exceed .4-foot candles at all property lines and that any light pole does not exceed 25 feet
in height.
Lieutenant Banick states in his memorandum on page 25 that preper lighting and an alarm system
would be advantageous in decreasing the opportunity for criminal activity on the site. Therefore,
proper lighting that adds. secudty while not causing negative impacts to the adjacent residential
properties will be important.
Other Comments
Police: In addition to the above-mentioned comments, Lieutenant Banick suggests limiting the hours
of operation to ensure no noise complaints from adjacent residential properties. This concern was
also expressed by an adjacent residential property owner, as outlined in the citizen comments on
page 6. Staff concurs with these concerns and recommends that there be no noise-making business
activity conducted in the lot, or made by vehicles entering or leaving the lot, between 7 p.m. and 7
a.m., MondaY through Saturday, or all day Sunday as required by code.
Building Department: Dave Fisher, Building Official, states in his memorandum on page 26 that a
metal building of this size must be fully spfinklered. This information was shared with the applicants,
who are willing to install a sprinkler system.
Fire Department: Butch Gervais, Fire Marshal, states in his memorandum on page 27 that a metal
building of this size must have fire protection. Again, the applicants are aware of this requirement
and are willing to install a fire alarm.
RECOMMENDATIONS
Deny Erik Ohlson's and Stephanie Jacques' request for a conditional use permit for exterior
storage at 1949 Atlantic Street. The city is denying this request because:
Exterior storage will negatively impact the adjacent recreational trail (Gateway Trail)
and residential properties.
Exterior storage is not compatible to the proposed redevelopment opportunities
currently being studied by the city council for the surrounding properties.
Approve the attached resolution on pages 28 and 29. This resolution approves a conditional
use permit for Erik Ohlson and Stephanie Jacques to construct a 6,800-square-foot metal
building within the Business Commercial zoning district at 1949 Atlantic Street for a
landscaping business. The city council bases the permit on the findings required by code,
and the conditional use permit is subject to the following conditions:
No extedor storage is allowed, including equipment and supplies associated with the
business.
There shall be no noise-making business activity conducted in the lot, or made by
vehicles entering or leaving the lot, between 7 p.m. and 7 a.m., Monday through
Saturday, or all day Sunday as required by code.
Ohlson Landscaping 3 January 28, 2003
c. All construction shall follow the site plan approved by the city. The director of
community development may approve minor changes.
d. The conditional use permit shall be reviewed by the city council in one year.
Approve the plans date-stamped December 31, 2003, for a 6,800-square-foot metal building
for the Ohlson Landscaping, Inc. business located at 1949 Atlantic Street. Approval is based
on the following conditions:
a. Repeat this review in two years if the city has not issued a building permit for this
project.
b. Provide the following for city staff approval before the city issues a grading or building
permit:
1) A detailed grading, drainage and erosion control plan, subject to the city
engineer's approval.
2)
Revised elevations showing the following:
a) Brick or stone wainscoting on the north, east and west elevations.
b)
c)
Four dormers on the roof facing Atlantic Street.
The metal panels and standing seam roof must be constructed of
natural colors.
3)
Building samples of metal panels, standing seam roof, trim, doors, and
wainscot.
4)
A revised landscape plan that shows the following:
a) Additional evergreen trees for screening of the building from Atlantic
Street to be located on the southeast side of the lot.
b)
Native plantings along the north side of the property, adjacent the
Gateway Trail.
c)
d)
Turf establishment plan.
Landscaping within any proposed rainwater garden. If the basin area
will only be seeded, the area must be vegetated with native grasses
and forbes. The mix design must be preapproved by the city in
advance of seeding.
e)
The size and species of all plantings.
Underground irrigation for all landscaped areas, excluding rainwater
gardens.
Ohlson Landscaping 4 January 28, 2003
Co
5)
A detailed photometric plan for all proposed outdoor lighting, subject to staff
approval.
6)
Plans for a trash-dumpster enclosure. The gates shall be 100 percent opaque
and the materials and colors of the enclosure shall be compatible with those of
the new metal building. This plan shall be sUbject to staff approval.
7)
A letter of credit or cash escrow for all required exterior improvements. The
amount shall be 150 percent of the cost of the work.
Complete the following before occupying the metal building:
1 ) Install all required exterior improvements.
If any required work is not done, the city may allow temporary occupancy if:
1)
The city determines that the work is not essential to the public health, safety or
welfare.
2)
The above-required letter of credit or cash escrow is held by the City of
Maplewood for all required extedor improvements. The owner or contractor
shall complete any unfinished extedor improvements by June I if occupancy of
the building is in the fall or winter, or within six weeks of occupancy of the
building if occupancy is in the spdng or summer.
All work shall follow the approved plans. The director of community development may
approve minor changes.
Ohlson Landscaping
5 Janua~ 28,2003
CITIZEN COMMENTS
Staff surveyed the property owners within 350 feet of this site to get their opinions of this proposal.
Out of the 20 properties surveyed, five responses were received as follows:
For
Ray and Agatha Trotter, 1202 E. Ryan Avenue, Maplewood: "Great place for a garden center. I'm
looking forward to using their services and products."
Against
MapleW°od Ventures LLC, 18465 Ixonia Avenue, Lakeville, MN (Deleano Benjamin, Maplewood
Bowl Maplewood'Ventures, LLC): "1 would normally be supportive of any form of improvement on the
site in question. However, in all fairness to the City of Maplewood, and to Mr. Ohlson, I believe the
following should be taken into account. 1) I am not sure a metal building with outside storage of
landscaping equipment and supplies would be that much of an improvement; and 2) Far more
importantly, we need to take into account that this construction would not work at all properly into the
future planning for rebuilding a revitalized new downtown Maplewood. I am prepared to make my
presentation for a European Style Centrum to the City Planners and hope to have a preliminary
meeting this week or next.'
Bernard E. & Jeanne M. Kelcher, 1210 Ryan Avenue E., Maplewood: "The noise levels in our
residential area are already extremely high from other nearby industrial-type businesses adjoining the
proposed structure. We're already subjected to loud car noises and barking guard dogs from the
existing businesses at all hours of the day and night. The proposal should include a fence (such as
on freeways) that lowers noise levels and will not distract from the natural beauty of the Gateway
Trail and surrounding areas like one more additional metal structure will."
Concerns
Stephen M. & Nora J. Oerter, 1224 Ryan Avenue E., Maplewood: "1 have no problem with the
buildings. However, I do have some issue with late evening - night noise. Perhaps a compromise
can be achieved."
Timothy S. & Terri Kershaw, 1250 Ryan Avenue E., Maplewood: "As long as the trees on the trail
are undisturbed, I support their plan. To have their vehicles and machinery out of sight will improve
the overall look of the area."
Ohlson Landscaping 6 January 28, 2003
REFERENCE INFORMATION
SITE DESCRIPTION
Site Size:
Existing Land Use:
31,578 square feet (.72 acres)
Landscape Business Vehicle Storage
SURROUNDING LAND USES
North:
South:
East:
West:
Gateway Trail and Single Family Homes
George's Auto Body/Car Wash/Apartment
Maplewood Bowl
Al's Auto Service/D & D Towing/Cellular Tower
PLANNING
Land Use Plan:
Zoning:
B-C (Business Commercial)
B-C (Business Commercial)
ORDINANCE REQUIREMENT
Section 36-151(b)(4) requires a CUP for the exterior storage of goods or materials within the
Business Commercial zoning district.
Section 36-151 (b)(6) requires a CUP for a metal building within the Business Commercial zoning
district if the following findings are met:
No more than 20 percent of the building would be visible from streets or the highest
topographical point of the nearest residential lot lines.
The building would not be of lesser quality than surrounding development. If the screening is
removed or dies and the owner does not replace it, the city council may require that the owner
remove the building. If the value of the building exceeds $25,000, the city council shall allow
at least a five-year amortization period.
CRITERIA FOR APPROVAL
See attached CUP requirements and standards on pages 28 and 29 for approval.
Ohlson Landscaping
7 Janua~ 28,2003
APPLICATION DATE
The city received a complete CUP application for this request on December 31, 2002. Minnesota
Statutes, Section 15.99 requires that the city take action within 60 days of receiving a complete
application fora land use proposal. Therefore, city action iS required on this request by March 1,
2003.
P: Sec 16~.Ohlson Landscaping
Attachments:
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
Edk Ohlson's Letter Dated September 27, 2002
City Location Map
Location Map
Land Use Map
Zoning Map
Site Plan
Grading Plan
Elevations
Floor Plan
Pictures
Dept. of Nat. Resource's Letter Dated January 21, 2003
Assistant City Engineer Chris Cavetrs Memorandum Dated January 28, 2003
Lieutenant Banick's Memorandum Dated January 23, 2003
Building Official Dave Fisher's Memorandum Dated January 3, 2003
Fire Marshal Butch Gervais' Memorandum Dated January 3, 2003
Conditional Use Permit Resolution
Plans (Separate Handout)
Ohlson Landscaping 8 January 28, 2003
Attachment 1
1706 Barclay Street
Maplewood, MN 55109
{651) 748-1566 Fax: {651) 779-4246
September 27, 2002
City of Maplewood
1830 County Road B East
Maplewood, MN 55109
Dear Shann:
Included are the items and documents requested to begin processing our request for improving
our property at 1949 Atlantic Street, Maplewood, MN 55109.
Currently, we are using this property as a meeting place for our employees in the mornings and
where they leave their vehicles. After reviewing that days specific job, we and our employees
load up the necessary tools and equipment and leave in the company vehicle(s) needed to
perform that days duties. To date, this land has been used for company vehicle and equipment
storage, as well as excess landscaping materials, which are stored until needed at a later date.
We do have a storage container on the property to securely lock up our smaller tools and
equipment.
Our business has been steadily growing at a rate that requires us to conduct our business in a
more professional environment. Our employees need an enclosed building to conduct their
general maintenance on equipment (i.e. tire changes, oil changes, small engine tune-up, etc.),
instead of attempting to perform these duties in the rain, mud or freezing temperatures.
We are proposing to build a building approximately 50'd x 100'1. This building will include an
area for (2) two office personnel sealed offfrom the maintenance and service area. This building
is strictly to be used as a working space for 2 to 4 office staffand 3 vehicle bays, each separated
from the other.
We are fortunate to experience phenomenal growth in our company, and have strived for years to
get where we are today. That is why we desperately need to utilize this property in a manner,
which is functional and appealing. Being in the landscape and property maintenance service, we
will be designing the property as appealing to the eye and to blend with the area surrounding it.
We look forward to hearing from you and working with you to create an exceptional addition to
the Lincoln Park area.
Most Sincerely,
Erik M. Ohlson
CEO, Pres./Ohlson Landscapes, Inc.
Attachment 2
Little Canada
North St. Paul
1949 Atlantic Street
North St. Paul
St. Paul
S
City Location Map
10
Attachment
Proposed Ohlson
Landscaping Site
~~J City Open Space
I I I
'¢',[,'1.,, I~ ~ ]1. ~, . ~ ~
N
Location Map
11
Attachment 4
1949 Atlantic Street
rost
City Open Space
Location of New
Roundabout
Legend
Light Manufacturing
Heavy Manufacturing
Neighborhood Commercial
Commercial Office
Limited Business Commercial
Business Commemial Modified
Business Commercial
Small Lot Single Dwelling Resi
Single Dwelling Residential
Double Dwelling Residential
Low Multiple Dwelling Resident
Medium Multiple Dwelling Resid
High Multiple Dwelling Residen
30000 Residential Estate
40000 Residential Estate
Park
Open Space
School
city
Govemment
Library
Cemetery
Fire Station
12
Land Use Map
Attachment 5
Frost Avenue
N
S
Legend
Light Manufacturing
Heavy Manufacturing
Neighborhood Commercial
Commercial Office
Limited Business Commercial
Business Commercial Modified
Business Commercial
Shopping Center
Small Lot Single Dwelling Residential
Single Dwelling Residential
Double Dwelling Residential
Low Mulitple Dwellings
High Multiple Dwelling Residential Condo
Planned Urban Development
Residential Estate (30,00 sq fi)
Residential Estate (40,00) sq It)
Farm
Zoning Map
13
Site Plan
s
Attachment 6
14
N
Att, 7
I
Grading Plan
15
Attachment 8
/I
Elevations
16
q-
<
Attachment 9
Floor Plan
BUILDING HI:IGt~T 14'-0°
17
Attachment 10
18
21
· !
Attachment ll
Minnesota Department of Natural Resources
Area 3B Trails & Waterways
1200 Warner Road, St. Paul, MN 55106.
Office (651) 772-7937; Fax (651) 772-7977
January 21, 2003
City of Maplewood
Office of Community Development
Attn: shann Finwall
1830 East County Road B
Maplewood, MN 55109
Subject: Response to Ohloson Landscaping, 1949 Atlantic Street - Neighborhood Survey
This letter is in response to a Neighborhood Survey for Ohlson Landscaping sent on January 2, 2003 to the State
of Minnesota Department. of Natural Resources (DNR) from the City of Maplewood. The DNR, Trails &
Waterways Division manages the Gateway State Trail that is adjacent to the proposed development at 1949
Atlantic Street in Maplewood.
The DNR Gateway State Trail wants to be a good neighbor and have good neighbors along the trail corridor.
Concerns for the trail include encroachment, trespass, visual quality, and dumping from adjacent landowners.
For this proposed development the DNR requests that the business respect the property boundary. We would
prefer a fence to define the property line and to retain the business materials. All bins and buildings need to
retain the desired contents as intended. There should be no grading, or construction of facilities that negatively
affect the vegetation or water drainage on the Gateway State Trail.
it would be preferred if there was some native vegetation to visually buffer the trail corridor from the business
site. Eventhough this is an urban environment, it is the intent of the DNR to manage for native plants and
animals along the trail and we encourage and appreciate when adjacent landowners add to the "green corridor".
Thank you for asking for our comments on this proposed development. If you have any questions, please
contact me.
Sincerely,
Suzann Willhite
Area Trails and Waterways Supervisor
suzann, willhite ~dnr. state, mn. us
eno:
22
Attachment 12
Engineering Plan Review
PROJECT: Ohlson Landscapes, Inc.
PROJECT NO:
REVIEWED BY: Chris Cavett and Erin Schacht
Maplewood Engineering Department, January 28, 2003
Ohlson Landscaping is proposing to construct a metal pole building at 1949 Atlantic Street. The
proposal includes.resurfacing the parking area with bituminous for 10 parking stalls and leaving
the remainder of the parking area as a gravel surface. The applicant has proposed to treat runoff
from the site with two on-site ponds.
The applicant's engineer should discuss this review and their revisions with Chris Cavett,
Assistant City Engineer before re-submittal.
The following issues shall be addressed:
1. Site plan and grading plan do not agree with each other. No consideration has been given
to the ponding areas on the site plan.
The city would be open to the applicant constructing a single larger treatment/detention
basin that extends partially into the Atlantic Street fight-of-way. Maintain a minimum
distance of 20-feet from the centerline of Atlantic with any grading. Consider creating
what in essence will appear as a broad, shallow ditch fi'om the drive to the property line.
The proposed pond on the north could be eliminated with a vegetated swale, (or
infiltration trench), that would drain towards the east then turn south under the drive and
into this larger east basin.
o
Construction and discharge of the north basin will require that the applicant obtain an
easement and permit from the Minnesota Department of Natural Resources, (Gateway
Trail).
4. Storm sewer must be extended between the east pond/basin to the existing storm sewer
on Atlantic Street.
The pond(s) must meet NURP design requirements and NURP calculations shall be
submitted to the city for review. An alternative to the NURP pond is to incorporate other
Best Management Practices (BMPs) in the design to adequately treat storm water. For
more information on alternative BMPs, please see the Metrocouncil BMP Manual at their
web site: http://www.metrocouncil.org/enviroment/Watershed/bmpmanual.htm
NOTE: Because of the sandy soils generally found in this area, the applicant is strongly
encouraged to consider constructing the basin(s) as bio-infiltration basins (rainwater
gardens). The basins should be designed to infiltrate runoff from a 1.5" storm event.
Rock infiltration sumps should be added to the basin along with appropriate landscaping
in and around the basin(s).
Rock infiltration sumps can be added to the proposed ponds to improve infiltration. The
sumps should consist of 1.5" of clean, clear rock wrapped in Type 5 geotextile filter
fabric, (felt). The top of the rock infiltration sumps shall be placed about'l 2 inches below
23
the finished bottom of the basin. Provide a detail and description in the plan of how the
contractor will prepare the rock sumps.
Provide a turf establishment plan and landscaping plan for the site. A perennial or shrub
rainwater garden design may be proposed. If the basin area is only intended to be seeded,
the area must be vegetated with native _grasses and forbes. The mix design must be
preapproved by the city in advance seeding.
Maintain a minimum 3:1 grade on the basin slopes. For slopes steeper than 3:1, specific
permanent erosion control measures must be addressed on the grading and landscape
plans.
The slopes to the basin(s) must be protected from erosion. As proposed there has been no
consideration on how the basin slopes will be prevented from eroding. Consider,
including catch basin pickups in the storm sewer design to convey runoffto the basin(s).
The applicant has proposed to maintain the storage area as a gravel surface. No
consideration has been given in the design to address sediment and fmcs from being
washed into the basin(s) and into the city storm system. Provide an adequate vegetated
filter strip between the gravel surface and the inlet to the basin(s), or consider using a
sump design in a structure that precedes the outlets to the basin(s). Periodic cleaning of
the sump would be required. A maintenance agreement would be required by the city.
Any stockpile areas must be adequately contained to prevent contamination to the storm
sewer system. All stockpiles must be housed internally or a treatment structure must be
included in the storm sewer design.
10. Provide silt fence along the entire north and east sides of the lot to prevent erosion and
sedimentation in the low areas.
11. If this property is to be served by public utilities, 6" water main must be extend north
from the existing stub at the north side of Frost Avenue. Water main can be installed
privately by the applicant through a developer's agreement, or be petitioned and assessed
back to the benefiting properties through a public improvement process. In either case,
coordination, review and approval must be made through St. Paul Regional Water
Services.
12. Submit revised plans to include all utility work (sewer, water and storm).
13. The city engineer shall approve restoration plan of the street. Minimum trench pavement
restoration for Atlantic Street shall be with 8-inches of aggregate base and 2-inches of
bituminous. (This is less than the existing street standard due to the condition of Atlantic
Street.)
14. The drive entrance shall be paved between the street and parking lot.
24
Attachment 13
Memo
To~
cc:
Date:
R~
Shann Finwall, Associate Planner"
Lieutenant John Banick ~
Chief Thomalla
1/23/2003
PROJECT REVIEW-Ohlson Landscapes, Inc.
I have reviewed the attached project proposal and currently have the following concerns:
1. Will this property have adequate lighting?
Will the building have an alarm system?
What are their hours of operation and will they be using heavy equipment to load
trucks?
As you know, this property is in a desolate location. Therefore, I am concemed about the potential
increase in theft, criminal damage, burglary, and other incidents that our department will be required to
respond to and investigate. Dudng 2002, our department handled seventy-three theft, twenty-eight
damage to property, and fifteen burglary incidents in this neighborhood (grids 52 and 53). Obviously,
proper lighting and an alarm system would be advantageous and decrease the opportunity for criminal
activity.
However, my main concern is the hours of operation and use of heavy equipment. This type of
business has the potential to create a considerable number of noise complaints during the peak
season. Frequently, land.s~-.a, pe workers start very early in the morning and work as late as possible.
With a quiet established neighborhood just north of this property, I am concerned about the increase in
noise that could adversely affect our current residents. Can we restrict the hours of operation at this
location?
If you have any questions, please contact me at extension 4502.
25
Attachment 14
MEMO
To~
From:
Date:.
Shann Finwall, Associate Planner
David Fisher, Building Official
01-03-03
RE:
Proposed project at 1949 Atlantic Street, a 6,800 square
foot building.
Based on the information provided there would be a flammable waste
interceptor required and Chapter 1306 of the State Building Code
would require the building to be fully sprinklered. There may be a
one-hour firewall required between the office and the service garage
depending upon the use. Bathrooms would also be required. The
building and parking would be required to meet all the accessibility
requirements of Chapter 1341 of the State Building Code. Also the
rules for the architects and engineers will require a design
professional to submit plans for the building permit.
26
Attachment 15
Project Review Comments
Date:
From:
Project:
Planner:
January 3, 2003
Butch Gervais, Fire Marshal
Ohlson Landscape Building
Shann Finwall
Commems:
According to the information provided this building would need to have fire protection
installed: The owner states that the building will be 6,800 square feet and used as a
service area and business office.
So with this information under the code (1306) service garages of 3,000 square feet or
more needs fire protection and parking garages of 5,000 square feet or more needs fire
protection.
This building appears to be falling under the code requirements (1306).
Maintain fire department access road of not less than 20 feet and needs to be a surface
that can be driven on all year round.
27
Attachment 16
CONDITIONAL USE PERMIT RESOLUTION
WHEREAS, Erik Ohlson and Stephanie Jacques applied for a conditional use permit for the
construction of a metal storage building that is 6,800 square feet in area and 23 feet, 6 inches in
height within the Business Commercial zoning district;
WHEREAS, this permit applies to property located at 1949 Atlantic Street, Maplewood,
Minnesota. The legal descnption is:
Vacated alley adjacent and accruing and except the South 10 feet, the East 8.57 feet of Lot
14; also, the East 8.57 feet of Lots 11 through 13; also Lot 6, except the South 10 feet of that
part West of the East 103.57 feet of said Lot 6; and all of Lots 7 through 10, all in Block 3,
Lincoln Park, Ramsey County, Minnesota.
WHEREAS, the Ramsey County Property Identification Number for this property is
16-29-22-14-0089;
WHEREAS, the history of this conditional use permit is as follows:
On February 3, 2003, the planning commission recommended that the city council approve
the conditional use permit.
On ,2003, the city council held a public hearing. City staff published a
notice in the Maplewood Review and sent notices to the surrounding property owners. The
council conducted the public hearing whereby ali public present were given a chance to speak
and present written statements. The city council also considered reports and
recommendations from the city staff and planning commission.
NOW, THEREFORE, BE IT RESOLVED that the city council approves the above-described
conditional use permit based on the building and site plans. The city approved this permit because:
The use would be located, designed, maintained, constructed and operated to be in
conformity with the city's comprehensive plan and Code of Ordinances.
2. The use would not change the existing or planned character of the surrounding area.
3. The use would not depreciate property values.
The use would not involve any activity, process, materials, equipment or methods of operation
that would be dangerous, hazardous, detrimental, disturbing or cause a nuisance to any
person or property, because of excessive noise, glare, smoke, dust, odor, fumes, water or air
pollution, drainage, water runoff, vibration, general unsightliness, electrical interference or
other nuisances.
The use would generate only minimal vehicular traffic on local streets and would not create
traffic congestion or unsafe access on existing or proposed streets.
The use would be served by adequate public facilities and services, including streets, police
and fire protection, drainage structures, water and sewer systems, schools and parks.
28
/. I ne use woulo not create excessive aooitional costs for public facilities or services.
R The use would maximize the preservation of and incorporate the site's natural and scenic
features into the development design.
9. The use would cause minimal adverse environmental effects.
Approval of the conditional use permit is subject to the following conditions:
1 No exterior storage is allowed, including equipment and supplies associated with the
business.
2. There shall be no noise-making, business activity conducted in the lot, or made by vehicles
entering or leaving the lot, between 7 p.m. and 7 a.m., Monday through Saturday, or all day
Sunday as required by code.
3. All construction shall follow the site plan approved by the city. The director of community
development may approve minor changes.
4. The conditional use permit shall be reviewed by the city council in one year.