6. Design Review
a. Office Depot and Pier 1 Imports - Southeast corner of 2570 White Bear
Avenue and Lydia Avenue, Centres Group
b. Pineview Estates Condominiums- County Road D, Goff Homes, Inc.
c. Hill-Murray High School Expansion-2625 Larpenteur Avenue
7. Visitor Presentations
8. Board Presentations
9. Staff Presentations
a. CDRB Volunteers Needed for June 14 and 28
10. Adjourn
p:com-dvpt\cdrb.agd
WELCOME TO THIS MEETING OF THE
COMMUNITY DESIGN REVIEW BOARD
This outline has been prepared to explain the review process of this meeting. The
review of an item usually follows this format.
1. The chairperson of the meeting will announce the item to be reviewed.
The chairperson will ask the applicant or developer of the project up to the podium
to respond to the staff's recommendation regarding the proposal. The Community
Design Review Board will then discuss the proposed project with the applicant.
The chairperson will then ask the audience if there is anyone present who wishes
'to comment on the proposal.
After everyone is the audience wishing to speak has given his or her comments,
the chairperson will close the public discussion portion of the meeting.
5. The Board will then discuss the proposal. No further public comments are allowed.
6. The Board will then make its recommendations or decision.
Most decisions by the Board are final, unless appealed to the City Council. You
must notify the City staff in writing within 15 days to register an appeal.
jw\forms\cdrb.agd
Revised: 11-09-94
MINUTES OF THE MAPLEWOOD COMMUNITY DESIGN REVIEW BOARD
1830 COUNTY ROAD B EAST, MAPLEWOOD, MINNESOTA
APRIL 27, 1999
CALL TO ORDER
Chairperson Ledvina called the meeting to order at 6 p.m.
I1. ROLL CALL
Matt Ledvina Present
Marie Robinson Present
Ananth Shankar Absent
Tim Johnson Present
III. APPROVAL OF MINUTES
April 13, 1999
IV.
VI.
Boardmember Johnson moved approval of the minutes of April 13, 1999, as submitted.
Boardmember Robinson seconded. Ayes--all
The motion passed.
APPROVAL OF AGENDA
Boardmember Robinson moved approval of the agenda as submitted.
Boardmember Johnson seconded. Ayes--all
The motion passed.
UNFINISHED BUSINESS
There was no unfinished business.
DESIGN REVIEW
A. Pep Boys Automotive Center--South of 2570 White Bear Avenue
Secretary Tom Ekstrand presented the staff report. He said a revised plan was brought to the
Maplewood Planning Commission meeting on April 19 that showed the site shifted northerly
five feet. Mr. Ekstrand had not received a copy of this revised site plan. However, this
alteration has been addressed by a condition in the report.
Jennifer Posma of Hansen Thorp Pellinen and Olson said the applicant was in agreement
with all of the staff recommendations and the additional conditions required by the planning
commission. She brought a revised plan that showed the entire paving and building shifted
north on the site by five feet to provide a larger green space area between the pavement and
the professional building to the south. They were able to do this by reducing the green space
on the northerly portion of the lot. Ms. Posma said additional tree screening was added on
Community Design Review Board
Minutes of 04-27-99
-2-
the south between Pep Boys and the professional building. She also said the retaining wall
has been shortened slightly.
Ms. Posma noted another minor alteration was to move two stalls previously shown in the
overflow bump-out area and the tire and trash enclosure to allow better drainage. This will
also provide better circulation for any trucks servicing the trash and tire enclosure. She said
this will be screened with white cedar. Mr. Ekstrand pointed out that the shift to the north was
done at staff's request because the neighboring property owner to the south asked for a little
more buffering between the two sites.
Boardmember Johnson asked if the trees selected by the applicant were within the city's
guidelines. Mr. Ekstrand said the species were fine but he did not know about the size.
Chairperson Ledvina inquired about the curb cut on the north portion of the property which is
not symmetrical with the existing cut at National Tire and Battery. Ms. Posma said this cut
was designed to allow adequate turning radius for trucks entering the site. The board and
staff discussed how vehicles would have southbound access to White Bear Avenue. It was
determined that the only way to make a right turn would be through the NTB site.
Thomas Ryckman of Casco Corporation in St. Louis, the architects/engineers for the project,
was present. Mr. Ryckman showed a colored elevation that depicted what the building would
look like. He said they were blending the building materials from the two adjacent sites.
Materials used on the exterior will be a combination of brick, EIFS and split-face concrete
masonry (CMU). The building will basically be earthtone with various "Pep Boy" red accents.
Mr. Ryckman described the construction of the scissor-lift dock area and felt there was
sufficient clearance for semi-trucks. Mr. Ryckman said there would be standard roof vents,
four rooftop units and a small satellite dish on the roof. The signage will be illuminated.
Chairperson Ledvina had a question about the red banding on the east side of the building.
Mr. Ryckman said this is actually gutter and downspouts that are painted "fire-engine" red.
Mr. Ledvina asked if there would be an objection to eliminating this red on the backside of the
building. Mr. Ryckman did not object to changing the gutters and downspouts to an earthtone
to match the building. He also said that Pep Boys uses a shoebox light fixture which shines
directly down to keep the lighting on the site.
Boardmember Johnson moved the Community Design Review Board:
Co
Approve the plans, date-stamped March 5, 1999, for proposed Pep Boys Automotive
Center south of 2570 White Bear Avenue, based on the findings required by the code.
Approval is subject to the following conditions:
1. Repeat this review in two years if the city has not issued a building permit for this
project.
2. Before getting a building permit, the applicant shall:
ao
Dedicate a wetland-buffer easement. This easement shall describe the boundary
of the buffer and prohibit any building, mowing, cutting, filling or dumping within
the buffer, except for required landscaping and seeding. The applicant shall
record the deed for this easement before the city will issue a building permit. The
Community Design Review Board
Minutes of 04-27-99
-3-
The
a,
wetland-buffer easement shall cover all of the Pep Boys property east of the
parking lot curbing.
b. Revise the site plan by widening the southerly landscaped strip by five feet. This
five-foot widening is derived from narrowing the northerly green area by five feet.
c. Submit grading, drainage, utility and erosion control plans to the city engineer for
approval.
d. Revise the rear building elevations to provide rock-face concrete block, instead of
flat concrete block, painted to match the color and detailing on the front and sides
of the building.
e. Combine the three lots and two vacated street rights-of-way that comprise this
site into one legally-described parcel.
f. Dedicate and record cross easements for access between Pep Boys and National
Tire and Battery if this easement has not yet been established.
3. applicant shall complete the following before occupying the building:
Install a reflectorized stop sign at the southerly exit and a handicap-parking sign
for each handicap parking space.
b. Post a "no left turn" sign at the southerly curb cut.
c. Provide continuous concrete curb and gutter all around the parking lot and
driveways.
d. Paint the rooftop mechanical equipment to match the building color if the units are
visible. (code requirement)
e. Construct the trash dumpster enclosure using the same materials and color as
the building. This enclosure shall have a 100 percent opaque gate.
f. Install an in-ground lawn irrigation system for all landscaped areas except for the
planted areas by the wetland behind the building. (code requirement)
g. Install signs at the edge of the wetland-protection buffer which prohibit any
building, mowing, cutting, filling or dumping within the buffer.
h. Provide site-security lighting as required by the code. The light source, including
the lens covering the bulb, shall be concealed so not to cause any nuisance to
drivers or neighbors.
4. If any required work is not done, the city may allow temporary occupancy if:
a. The city determines that the work is not essential to the public health, safety or
welfare.
VIII.
Community Design Review Board
Minutes of 04-27-99
-4-
The city receives a cash escrow or an irrevocable letter of credit for the required
work. The amount shall be 200 percent of the cost of the unfinished work. Any
unfinished landscaping shall be completed by June 1 if the building is occupied in
the fall or winter or within six weeks if the building is occupied in the spring or
summer.
5. This approval does not include the signs.
the sign permit process.
6. All work shall follow the approved plans.
approve minor changes.
Boardmember Robinson seconded.
Signage will be reviewed by staff through
The director of community development may
Chairperson Ledvina added a friendly amendment that neutral colors be used for the east
elevation trim, in place of the red, as well as downspouts and canopy.
Boardmember Robinson seconded the amendment.
Ayes--all
The motion passed.
VII. VISITOR PRESENTATIONS
There were no visitor presentations.
BOARD PRESENTATIONS
There were no board items on the city council meeting of April 26 so Ms. Robinson did not attend.
IX. STAFF PRESENTATIONS
A. Resolution of Appreciation for Mary Erickson
Boardmember Robinson moved acceptance of the resolution of appreciation for former board
member Marv Erickson.
Boardmember Johnson Ayesmall
The motion passed.
B. CDRB Volunteer for the May 10 Council Meeting: Mr. Johnson will attend this meeting.
C. CDRB Volunteer for May 24 Council Meeting: Mr. Ledvina will attend this meeting.
X. ADJOURNMENT
The meeting adjourned at 6:47 p.m.
TO:
FROM:
SUBJECT:
LOCATION:
DATE:
MEMORANDUM
City Manager
Thomas Ekstrand, Associate Planner
Office Depot and Pier 1 Imports
Southeast comer of White Bear Avenue and Lydia Avenue
May 13, 1999
INTRODUCTION
The Centres Group is asking for plan approval to build a 40,155-square-foot retail building for an
Office Depot and Pier 1 Imports. The proposed site is the Bruentrup Farm property at 2980
White Bear Avenue. Refer to the maps on pages 7-9. The proposed building would have an
extedor of rock-face concrete block and rock-face brick-pattern block. Refer to the building
elevations in the plans.
BACKGROUND
In January, 1999, the city council considered a request from the Maplewood Historical Society
that the city purchase the Bruentrup Farm. The historical society hoped to preserve it as a
reminder of Maplewood's heritage. After sedous consideration, including a study by Decision
Resources and an attempt to find financial support from Maplewood residents, the council found
that saving the farm was financially infeasible.
The historical society and the city are now jointly pursuing financial assistance from the state
legislature to help pay for moving the farm house, windmill, barn and granary to a site on County
Road D between Ariel Street and McKnight Road. The final answer from the state will be given
by May 17.
DISCUSSION
Wetland Code
The pond on this site is a Class-5 Wetland. The ordinance does not require a wetland-protection
buffer around Class-5 wetlands. The proposed development is in compliance with the city
wetland requirements.
Design Considerations
The building would be attractive. Staff recommends, however, that the entire north elevation be
treated with the same brick-pattern matedal as the west elevation. The north elevation faces
Lydia Avenue and should not transition from the brick-pattern to rock-face block.
Landscaping. Screening and Retaining Wall
The proposed landscaping would be attractive and would enhance the site. The screening code,
however, requires that the applicant provide a six-foot-tall and 80 percent opaque visual screen
between Concordia Arms and the proposed parking lot. The landscape plan should be expanded
in back to attain this 80 percent opaque screening for Concordia Arms.
The Concordia Arms management requested that their westedy berm be cut down to their
parking lot level and a screening fence be installed to provide buffedng between the two sites.
Staff feels that the berm is providing a substantial screen as it is, especially next to the
Concordia Arms parking lot. A combination of a screening fence, evergreens and berming could
be utilized to provide proper screening between the apartment building and the proposed project.
If the owners of Concordia Arms and the developer agree they feel the berm should be cut down,
the developer should submit a revised grading plan and a revised landscaping/screening plan for
staff approval.
The applicant has proposed a retaining wall around the pond. This wall would be eight to twelve
feet tall. The applicant should be required to install a protective guard rail at the top. The design
of and materials of this wall should be submitted to staff for approval.
Parking
The applicant is meeting the parking code with the proposed 196 spaces. The four extra "proof-
of-parking" spaces are not necessary.
Roof-EQui_oment Screening
Roof-top mechanical equipment that is visible from roadways and nearby commercial properties,
must be painted to match the building. The roof-top equipment must be screened, however,
from Concordia Arms Apartments to the east.
Existing Driveway O_oenings
There are two existing driveway curb cuts to the farm sitc one along each street. The applicant
should close these and restore the ground.
ParkinQ Lot Connection to Edina Realty
This ddveway connection only benefits Edina Realty. Staff does not have any objection to this
connection, but recommends that the two property owners grant each other reciprocal access
easements.
Sidewalks
The applicant should extend the concrete sidewalks along both of their street frontages.
Presently, there is a sidewalk along Lydia Avenue in front of Concordia Arms that ends at the
applicant's east lot line. There is also a sidewalk in front of Edina Realty that ends at the south
edge of Edina's entrance drive. Staff recommends that the applicant provide sidewalks along
both of their street frontages as well as the short section of sidewalk on Edina Realty's property
between Edina's driveway and the common lot line.
RECOMMENDATION
Approve the plans, date-stamped Apd127, 1999, for proposed Office Depot and Pier I Imports
at the southeast comer of White Bear Avenue and Lydia Avenue. Approval is subject to the
following conditions:
1. Repeat this review in two years if the city has not issued a building permit for this project.
2. Before getting a building permit, the applicant shall:
ao
Submit grading, drainage, utility and erosion control plans to the city engineer for
approval. This plan shall also detail the closing of the two existing curb cuts, the new
street curb installation and ground restoration.
b. Revise the north elevation of the building to provide the same brick-pattern detailing and
color scheme as proposed on the west elevation.
c. Provide plans of the retaining wall for staff approval showing a protective railing at the
top. The design and color of the retaining wall shall be compatible with the building.
d. Revise the landscape plan for staff approval providing for a six-foot-tall and 80 percent
opaque screen next to the Concordia Arms Apartments.
e. If the owners of Concordia Arms and the developer agree that they feel the Concordia
Arms berm should be cut down, the developer should submit a revised grading plan and
a revised landscaping/screening plan for staff approval.
The applicant shall complete the following before occupying the building:
a. Install a reflectodzed stop sign at both exits and a handicap-parking sign for each
handicap parking space.
b. Provide continuous concrete curb and gutter all around the parking lot and driveways.
c. Remove the two existing driveway curb cuts and restore the ground and street curbing in
both areas.
d. Install the guard rail on top of the retaining wall.
e. Paint the rooftop mechanical equipment to match the building color if the units are visible
from the streets and nearby commercial properties. Provide screening around roof-top
mechanical equipment if visible from Concordia Arms. (code requirements)
f. Construct the trash dumpster enclosure using the same materials and color as the
building. This enclosure shall have a 100 percent opaque gate.
g. Install an in-ground lawn irrigation system for all landscaped areas. (code requirement)
h. Provide site-security lighting as required by the code. The light source, including the
lenses covering the bulbs, shall be concealed or recessed so not to cause any nuisance
to drivers or neighbors.
Construct sidewalks along the Lydia Avenue and White Bear Avenue frontages to the
intersection of these streets. The sidewalks shall be ramped to meet the street grade at
the intersection and driveway crossings. The applicant shall also provide the short
section of sidewalk on the Edina Realty property between Edina's ddveway and their
north lot line.
4. If any required work is not done, the city may allow temporary occupancy if:
a. The city determines that the work is not essential to the public health, safety or welfare.
bo
The city receives a cash escrow or an irrevocable letter of credit for the required work.
The amount shall be 200 percent of the cost of the unfinished work. Any unfinished
landscaping shall be completed by June I if the building is occupied in the fall or winter or
within six weeks if the building is occupied in the spring or summer.
This approval does not include the signs. Signs will be reviewed by staff through the sign-
permit process.
All work shall follow the approved plans. The director of community development may
approve minor changes.
CITIZENS' COMMENTS
I surveyed the 19 property owners within 350 feet of this site. There were three replies.
Replies
1. Vergie Daniski, a resident of Concordia Arms, expressed concern about truck-exhaust odors.
2. Another resident of Concordia Arms called with concerns about truck fumes and requesting a
privacy fence on the west side of their property.
3. Barbara Kohlman, the manager at Concordia Arms, had the following comments:
a. The Lydia Avenue sidewalk should be extended to White Bear Avenue.
b. The city should acquire the portion of this site adjacent to Maplewood Hills Park and
provide community garden plots.
c. The tall berm along Concordia Arms' west lot line should be cut down to their parking lot
level to aid driver's visibility when exiting the apartment site. The developer should then
install a screening fence like the one Concordia Arms has on their east lot line.
5
REFERENCE INFORMATION
SITE DESCRIPTION
Site size: 6.26 acres
Existing land use: The Bruentrup Farm
SURROUNDING LAND USES
North:
South:
West:
East:
Lydia Avenue and the Plaza 3000 shopping center
Edina Realty and Maplewood Hills Park
White Bear Avenue, Twin City Federal and Firsbank
Concordia Arms Senior Housing apartments
PLANNING
Land Use Plan designation: BC
Zoning: F
Ordinance Requirements
Section 25-70 of the city code requires that the CDRB make the following findings to approve plans:
That the design and location of the proposed development and its relationship to neighboring,
existing or proposed developments, and traffic is such that it will not impair the desirability of
investment or occupation in the neighborhood; that it will not unreasonably interfere with the use
and enjoyment of neighboring, existing or proposed developments; and that it will not create traffic
hazards or congestion.
That the design and location of the proposed development is in keeping with the character of the
surrounding neighborhood and is not detrimental to the harmonious, orderly and attractive
development contemplated by this article and the city's comprehensive municipal plan.
That the design and location of the proposed development would provide a desirable environment
for its occupants, as well as for its neighbors, and that it is aesthetically of good composition,
materials, textures and colors.
p:sec2n\offdepot, mem
Attachments:
1. Location Map
2. Property Line/Zoning Map
3. Site Plan
4. Plans date-stamped April 27, 1999 (separate attachments)
D
SH~'RRE:N ~
AV~.
I
WHITE BEAR LAKE
dOHN'S ~
w KOHL.MAN
DE~ONT
Attachment 1
1. N. BARTE3..MY L
2. N. CHIPI:~"WA C
3. BRENWOOO CV.
NORTH ST. PAUL
LOCATION
MAP
MAPLEWOOD
MALL
BC
MAPLEWOOD
SQUARE
TCF BANK
FIRSTAR BANK
Attachment 2
/
~C
PLAZA 3000
JF
III lll.l-l_l
SiTE
CONCORDIA'
EDINA REALTY
OF MAPLEWOOD .-' ~ARK SiTE ,"
~_~ - MAPLL=WOOD ,'
CENTER
Attachment 3
SITE
PLAN
MEMORANDUM
TO:
FROM:
SUBJECT:
LOCATION:
DATE:
City Manager
Tom Ekstrand, Associate Planner
Design Review-Pineview Estates
North Side of County Road D, West of 1655 County Road D and Maple Ridge
Apartments
May 18, 1999
INTRODUCTION
Mr. Pat Goff, of Goff Homes, is requesting approval of a 72 unit condominium development on
County Road D. Refer to the maps on pages 4-6. The proposed buildings would have exteriors
of horizontal-lap vinyl siding with brick wainscot on the fronts (long elevations).
BACKGROUND
May 26, 1992: The community design review board approved the plans for Pineview Estates
Condominiums. The conditions of approval stated that this approval is good for two years. The
applicant, consequently, is repeating this review process since he had not started the project.
DISCUSSION
Building Design
This site plan is essentially the same as the one approved in 1992. The buildings are now three
stories tall and have two-car garages, however. The last proposal was for two-story buildings
with one-car garages. The current plans aro more attractive with the hip-roof design and the
shingle-roof detailing between the second and third floors.
Landscaping
The landscaping would be attractive. The sizes proposed meet code requirements.
Trash Disposal
Mr. Goff said that the owners of these condo units will contract for their own garbage disposal.
Thero will not be outdoor trash dumpsters.
RECOMMENDATION
Approve the plans (date-stamped May 7, 1999) for Pineview Estates, based on the findings
required by the code. The developer, Goff Homes, shall do the following:
1. Repeat this review in two years if the city has not issued a building permit for this project.
2. Before getting a building permit the applicant shall:
a. Submit a grading, drainage, utility and erosion control plan to the city engineer for
approval.
b. Submit a plan for the retaining wall to staff for approval. The developer shall install a
protective rail on top of the retaining wall if it is taller than four feet.
c. Submit the building color scheme to staff for approval.
3. Complete the following before occupying the building:
a. Replace property irons that are removed because of this construction.
b. Restore and sod damaged boulevards. Sod all landscaped areas, except the hillside to
the north which shall remain in its present state.
c. Install reflectodzed stop signs at both exits and addresses for the buildings and complex.
d. Install an automatic in-ground irrigation system with a rain sensor for all landscaped
areas, except for the hillside to the north.
e. Install continuous concrete curbing.
4. If any required work is not done, the city may allow temporary occupancy if:
a. The city determines that the work is not essential to the public health, safety or welfare.
b. The city receives a cash escrow or an irrevocable letter of credit for the required work.
The amount shall be 200 percent of the cost of the unfinished work. Any unfinished
landscaping shall be completed by June 1 if the building is occupied in the fall or winter or
within six weeks if the building is occupied in the spdng or summer.
5. The director of community development may
All work shall follow the approved plans.
approve minor changes.
-- REFERENCE INFORMATION
SITE DESCRIPTION
Site size: 5.98 acres
Existing land use: undeveloped
SURROUNDING LAND USES
North: Interstate 694, City of White Bear Lake
South: Undeveloped land planned for commercial use
East: A single dwelling and the Maple Ridge Apartments
West: A vacant lot owned by the City of Maplewood
PLANNING
Land Use Plan designation: R-3H (high-density residential)
Zoning: R3 (multiple-dwelling residential)
p:sec34-30~pineview.des
Attachments:
1. Location Map
2. Property Line/Zoning Map
3. Site Plan
4. Plans date-stamped May 7, 1999 (separate attachments)
Attachment 1
VADNAIS HEIGHTS
(~) OOUNTY ROAD
LAKE
Z
bJ
1. SUMMIT CT. ST. JOHN'S
2. COUNTRY~EW CIR. BLVD.
3. DULUTH Cl'.
LOCATION MAP
4
Attachment 2
..300'
--~-,o, 694
MAPLEWOOD ~
PONDING AF~f:~,~!
PROPOSED PINEVIEW ESTATES
COUNTY RD. D '
MAPLERIDGE
APARTMENTS
PROPERTY LINE I ZONING MAP
Attachment
1-694
COUNTY ROAD D
SITE
PLAN
MEMORANDUM
TO:
FROM:
SUBJECT:
PROJECT:
LOCATION:
DATE:
City Manager
Ken Roberts, Associate Planner
Conditional Use Permit Revision and Design Approval
Hill-Murray High School
2625 Larpenteur Avenue East
May 19, 1999
INTRODUCTION
Project Description
Mr. Greg Dehler, of Wold Architects and Engineers, is requesting city approval of the following
for Hill-Murray High School:
1. Revisions to the conditional use permit (CUP). They are proposing several changes to the
approved plans for the school. The city code requires a CUP for schools.
2. Design approval for an addition to the main entry of the school. This includes the
architectural, site and landscape plans for the project.
Refer to the maps on pages 7-12, the statement on page 13 and the plans (separate
attachment). Specifically, they want to:
Replace and expand the school's main entry. This is to enlarge the main floor lobby, provide
handicap accessibility to both floors and to enhance the building's image.
Add a drop-off drive to connect from the existing parking lot along the south side of the
school to the new main entrance.
3. In a future phase, add another entrance to the school property from Larpenteur Avenue and
64 parking spaces near their east property line.
Hill-Murray will do the improvements in stages as their funds allow.
BACKGROUND
On April 8, 1996, the city council approved a conditional use permit (CUP) for Hill-Murray to make
changes and improvements to their athletic fields. This approval was subject to ten conditions.
On July 14, 1997, the city council reviewed the CUP for Hill-Murray. At this meeting, the council
changed Condition 8 of the 1996 approval to read as follows: "Applicant may be required to plant
30 native species of trees for screening between the playing fields and the homes on Knoll
Circle, as may be determined at a future hearing on the Conditional Use Permit."
On May 11, 1998, the city council approved a wetland buffer setback variance and a conditional
use permit revision for the Hill-Murray Athletic Facilities. These requests were to update and
revise the plans that the city had approved for the school's athletic facilities in 1996 and in 1997
and were subject to several conditions. (See the conditions in the city council minutes starting on
page 14.)
DISCUSSION
Conditional Use Permit Revision
The proposed addition meets the findings for CUP approval and would be compatible with the
existing school and the development in the area. None of the proposed changes nor the addition
should cause any problems for the city or for the neighbors.
Design Considerations
Buildinq Aesthetics
The proposed building addition should be compatible with the existing building. The new entry
area would have skylights and many windows and doors with aluminum frames. However, the
proposed building elevations show areas of architectural precast concrete above the windows in
the addition. The city should require brick in these areas to ensure that the proposed addition is
compatible with the existing school building.
Wold Architects also submitted colored elevations for the proposed addition that show brick
columns that would match the existing school building. These colored elevations also show the
areas of precast concrete in a light yellow or tan color.
Parkin,cl Considerations
There are now 84 off-street parking spaces (including 2 handicap stalls) at Hill-Murray. The
proposed changes to the site, including the 64 additional spaces as proposed in the new easterly
parking lot, would raise the number of parking spaces to a total of 137 (including six handicap
stalls). The city code does not specify minimum parking requirements for schools, but the
number of spaces should be adequate for this facility.
Landscapin.q and Tree Removal
The proposed plans would include removing two, small caliper (less than eight-inches in
diameter) maple trees from the front of the school. The remaining existing trees in front of the
school and around the existing and proposed parking lots would provide sufficient landscaping.
The applicant is not proposing any new landscaping with the proposed addition and parking lot
changes, however.
Sidewalks
The applicant should provide a sidewalk along the west side of the new parking lot from the north
end of the lot to connect to the sidewalk to the front of the building. This is so a person using the
new parking lot can walk safely to the school's front doors without walking in the parking lot.
Roof-Equipment Screeninq
Roof-top mechanical equipment that is visible from roadways or nearby properties must be
painted to match the building. The city code no longer requires individual screens around such
units. The community design review board (CDRB) may require building designs that hide these
units, however.
RECOMMENDATIONS
Adopt the resolution on pages 18 - 20. This resolution approves revisions for the
conditional use permit for Hill-Murray school and athletic fields at 2625 Larpenteur Avenue
East. The city bases this approval on the findings required by ordinance. This approval is
subject to conditions of approval adopted by the city council on May 11, 1998, subject to the
following revisions (I have crossed out the deletions and underlined the additions):
..... =-- plans as noted below:
1. All construction shall follow the o,,~ .... plan o,,d ~, od,,,~ plsn
a. For the athletic fields, follow the plans date-stamped March 6, 1998.
b. For the school and entry addition, follow the plans date-stamped May 19, 1999.
The director of community development may approve minor changes. The school shall
move the proposed temporary storage buildings as far away from the wetland buffer as
possible to minimize the variance they will need.
The proposed construction for the front entry addition and drop-off drive must be
substantially started within one year of council approval or the permit revision shall end.
The council may extend this deadline for one year.
3._~. The city council shall review this permit annually to monitor the traffic and parking
situations related to the use of the athletic fields.
Any new lights shall be installed to meet the city code. This requires that they be
screened or aimed so they do not cause any light-glare problems on streets or
residential properties.
Dedicate and record a wetland-protection buffer easement. This easement shall
describe the boundary of the buffer and prohibit any building, mowing, cuffing, filling or
dumping within the buffer. The buffer shall follow the proposed chain-link fence line on
the plans for the athletic fields date-stamped March 6, 1998. The part of this wetland
buffer area that is already mowed lawn may remain as such. The school shall have the
contractor install the fence and swale while doing the adjacent field construction.
Post signs on the edge of the wetland-protection buffer prohibiting any building,
mowing, cutting, filling or dumping within the buffer. Wetland buffer signs in the
mowed area shall be placed at the edge of the lawn.
7_6. That portion of the proposed walking/running path that is within 50 feet of the wetland
shall be built with a pervious material.
8._~. Ensure that all bleachers and dugouts are at least 30 feet from the Sterling Street and
Larpenteur Avenue right-of-ways.
The city may require the applicant to plant 30 native species of trees for screening
between the playing fields and the homes on Knoll Circle, as may be determined at a
future hearing on the Conditional Use Permit.
3
Bo
10__+.
The school shall prepare for city approval a turf management plan for the athletic
fields. This plan shall include the mowing, watering and fertilizing practices that
the school will follow in the care of their athletic fields and grounds. The school
shall prepare and follow the plan so the practices will minimize the impact of the
storm water runoff on the nearby wetlands. The city must approve this plan before
issuin,q a buildin,q permit for the front-entry addition.
11 10.
Submit a grading and drainage plan for watershed district approval to provide
sedimentation control at the stormwater discharge point before it dumps into the
south wetland area.
Approve the plans, date-stamped March 19, 1999, for the parking lot changes and proposed
front entry addition to Hill-Murray High School at 2625 Larpenteur Avenue. The city bases
this approval on the findings required by the code and the project shall be subject to the
following conditions:
1. Repeat this review in two years if the city has not issued a building permit for this
project.
Before getting a building permit, the applicant shall submit the following for city staff
approval:
a. Grading, drainage, utility and erosion control plans to the city engineer.
bo
Detailed building elevations showing brick on the addition to match the existing
school building instead of the architectural precast concrete.
c. The finalized turf management plan as required by the conditional use permit.
3. The applicant or contractor shall complete the following before occupying the addition:
a. Replace property irons that are removed because of this construction.
b. Restore and sod damaged boulevards.
c. Install reflectorized stop signs at all exits, a handicap-parking sign for each
handicap-parking space and an address on the building.
d. Post a "no left turn" sign at the easterly curb cut.
e. Install continuous concrete curb and gutter all around the new parking lot and new
driveways. (code requirement)
fo
Paint the rooftop mechanical equipment to match the building color if the units are
visible. (code requirement)
go
Install site-security lighting as required by the code. The light source, including
the lens covering the bulb, shall be concealed so the light source in not visible and
so it does not cause any nuisance to drivers or neighbors.
ho
Install a six-foot-wide concrete sidewalk along the west edge of the new east
parking lot. This sidewalk shall run from the north end of the new parking lot to the
sidewalk that connects to the front of the school.
4. If any required work is not done, the city may allow temporary occupancy if:
a. The city determines that the work is not essential to the public health, safety or
welfare.
The city receives a cash escrow or an irrevocable letter of credit for the work. The
amount shall be 200 percent of the cost of the unfinished work. Any unfinished
landscaping shall be completed by June 1 if the addition is occupied in the fall or
winter or within six weeks if the building is occupied in the spring or summer.
All work shall follow the approved plans. The director of community development may
approve minor changes.
REFERENCE INFORMATION
SITE DESCRIPTION
Site size: 20 acres (athletic fields)
Existing land use: Hill-Murray High School and athletic fields
SURROUNDING LAND USES
North:
South:
West:
East:
Single dwellings and undeveloped property zoned F (farm residential)
Larpenteur Avenue and single dwellings
Sterling Street, ponds and The Maplewoods Apartments
St. Paul's Priory
PAST ACTION
August 24, 1992: Council approved a sign size variance for a 99-square-foot wall sign for
Hill-Murray. Code allowed 24 square feet.
5
PLANNING
Land Use Plan designation: S (school)
Zoning: R-3 (multiple dwelling residential)
Ordinance Requirements
Section 36-437(3) requires a CUP for schools.
Section 36-448(b) requires a CUP to enlarge a use for which a CUP is required.
Section 25-70 of the city code requires that the CDRB make the following findings to approve
plans:
That the design and location of the proposed development and its relationship to
neighboring, existing or proposed developments, and traffic is such that it will not impair the
desirability of investment or occupation in the neighborhood; that it will not unreasonably
interfere with the use and enjoyment of neighboring, existing or proposed developments;
and that it will not create traffic hazards or congestion.
That the design and location of the proposed development is in keeping with the character
of the surrounding neighborhood and is not detrimental to the harmonious, orderly and
attractive development contemplated by this article and the city's comprehensive municipal
plan.
That the design and location of the proposed development would provide a desirable
environment for its occupants, as well as for its neighbors, and that it is aesthetically of
good composition, materials, textures and colors.
Criteria for Conditional Use Permit Approval
Section 36-442(a) requires that the city council base approval of a CUP on ten standards. See
the standards in the resolution on pages 18 - 20.
p:sec13-29\hillmury.99
Attachments:
1. Location Map
2. Property Line/Zoning Map
3. Site Plan
4. Proposed Site Plan dated 5-19-99
5. Proposed Site Plan detail dated 5-19-99
6. Proposed Building Elevations dated 5-19-99
7. Statement of request dated May 4, 1999
8. 5-11-98 CUP conditions of approval
9. CUP Revision Resolution
10. Plans date-stamped May 19, 1999 (separate attachments)
RD.
Attachment 1
O' 1 700' 3400' ,5100' 6800'
EY COUNTY
'; HOME AND
GROUNDS
SCALE
NORTH SAINT
PAUL
(N. St. P.)
1. MARYJOE IN.
2. I~ERNEY AVE.
,3. MEADOW DR.
4. RIPLEY AVE.
GOODRICH
GOLF
COURSE
RIPLEY AVE.
KINGSTON
PRICE AVE.
AVE.
KINGSTON
IdCKNIGHT LN
CIR.
AVE.
IDAHO AVE.
NEBRASKA AVE.
OAK/~LL
ANCELA
5
! k~ICHAEL DR
2 REBECCA DR
3 PINETREE DR
4 I~RCH~EW DR
PINE TREE DR
6 8tRCHVlEw DR
7 ROLLING HILL~ DR
LOCATION
7
MAP
ANTELOPE WAY
AMBERJACK LN
BEVERDALE RD
BOBCAT LN
COUGER LH
AVE.
I~,.../MEADOW
Attachmen~c 2
'1
RIPLEY
1832,1
1822
2525
2520
R3
3
.---. ~ ' ST. PAUL'S PRIORY
· ,,, ,/ ,, _u HILL-MURRAY HIGH SCHOO~L~
"'. i ". /~ ~'~
,.....~..;~ ~, ,,-~m.-----.--;~------~__~f~-~L/~ PENTEUR AVENUE ~vc.-~
:,',~4' ~;,n ~li 2600m~ i t / m
.-'~';'L'2- ,~ I i I - f~' m l/ I
:E. IDAHO ~ J: . ¢ AVE. S ] I lummmlmmmmupm I
~l '-;'-i ',~ .... :~t~ I :" I :'m: ~ :''~,,~,t .,{'""'"""'"~," . ""]'d,~, ,I
-I,~',,~,~ ,~,,,~,~1,~1,,i ~J~ ~ , EA I
Attachment 3
PROPOSED
PARKING LOT
EXPANSION
iPROPOSED
ENTRY
EXPANSIO~
SITE
PLAN
Attachment 4
~ F~F~ --
~)C. NOT IN~LU~E~
UNI~ TH~ I'4AIN
L:~T~'K ~_I~[-~I~N
F~JE~T.
PRO~ PARKIN~
LOT EXPAhL~ION
(64) 5PACES~
l0
Attachment 5
... : .; ::.-:
: :Z:..'
· '-.
SITE PLAN
11
I
_
.................. ============================================
12
Attachment 6
TO:
FROM:
DATE:
COMM. NO:
Attachment 7
WOLD ARCHITECTS
AND ENGINEERS
305 ST. PETER STREET
ST. PAUl., MN 55102
651.227.7773
FAX 651.223.5646
Tom Ekstrand, Associate Planner - City of Maplewood Community Development
715-H TOI. LGA'rE ROAD
1~ ELGIN, IL 60123
Greg Dehle . 847.608.2600
FAX 847.608.2654
May 4, 1999
NET: HTTP//WWW. WOLDAE.COM
99003
SUBJECT: Modification to the Conditional Use Permit for Hill Murray School
The following is a written statement describing the intended use of the property based
on the City's criteria for approval.
The proposed project includes the replacement and expansion of the Hill Murray
School's main entry. The purpose of the expansion is to enlarge the main floor lobby,
provide handicap accessibility to both floors via an elevator, and to enhance the school
building's image. Through this enhancement, the existing adjacent property values
will not depreciated. As an existing school properly, the use will not change nor will
additional traffic be generated. Through the design, minimal impact to the existing
trees will be accomplished. Those which are scheduled to be removed, will be
relocated.
cc: Joseph Peshges, Hill Murray School
cj\99003~may99
13
Attachment 8
MINUTES OF THE MAPLEWOOD CITY COUNCIL
7~00 P.M.. Monday. May 11. 1998
Council Chambers. Municipal Building
Meeting No. 98-09
H. ~UBLIC_HF_A~INGS
1. 7~07 P.M. Hill-Murray High School Athletic Facilities (2625 Larpenteur Avenue East)
Wetland Buffer Setback Variance
Conditional Use Permit Revision
Mayor Rossbach convened the meeting for a public hearing regarding a wetland buffer
setback variance and condition use permit revision for Hill-Murray High School
athletic facilities.
Manager McGuire introduced the staff report.
Associate Planner, Ken Roberts presented the specifics of the report.
Commissioner Will Rossbach presented the Planning Commission report.
Mayor Rossbach opened the public hearing, calling for proponents or opponents.
following persons were heard:
$oe Peschges, President of Hill Murray School.
Larry Morgan, Vice President of Hill Murray Father's Club.
Joe Peschges (second appearance)
Sister Geran, Resident Nun of Hill Murray
The
f. Mayor Rossbach closed the public hearing.
Councilmember Koppen ~mYjm:~luced the following Resolution and moved its adoption'
98 -05 - 38
RESOLUTION WETLAND BUFFER SETBACK VARIANCE - HILL MURRAY ATHLETIC FIELDS
WHEREAS, Mr. Joseph Peschges of Hill-Murray High School applied for a variance from the
zoning ordinance.
WHEREAS, this variance applies to school property and athletic fields at 2625 Larpenteur
Avenue. The legal description is:
Part of the S ~ of the SE 1/4 of S 13, T 29N, R22W, Maplewood, Ramsey County, MN
WHEREAS, Section 36-196(h)(3) of the wetland protection ordinance requires a 50-foot-wide
wetland buffer.
WHEREAS. the applicant is proposing a zero- to 50-foot-wide wetland buffer.
WHEREAS, this requires a variance of zero to 50 feet.
WHEREAS, the history of this variance is as follows'
l. On April 20, 1998, the planning commission recommended that the City Council approve this
variance.
2. The City Council held a public hearing on May Il, 1998. City staff published a notice in
the Maplewood Review and sent notices to the surrounding property owners as required by
law. The Council gave everyone at the hearing an opportunity to speak and present
written statements. The Council also considered reports and recommendations from the
City staff and Planning Commission.
14
NOW. THEREFORE. BE IT RESOLVED that the City Council approve the above-described variance
for the following reasons:
1. Strict enforcement of the Code would cause undue hardship because of circumstances unique
to the property. The 50-foot-wide wetland buffer requirement would make redevelopment
of this site difficult. The difficulty was created by the new ordinance.
2. The variance would be in keeping with the spirit and intent of the ordinance, since the
applicant would improve the quality of the wetland buffer over its present state.
3. The proposal offers protection to the wetland and buffer for wildlife habitat and storm
water treatment, which also are functions of a wetland buffer.
Approval is subject to the applicant doing the following:
1. Follow the site, grading and edge treatment plans date-stamped March 6, 1998, subject to
any changes required by City staff or the Ramsey-Washington Metro Watershed District.
The school shall have the contractor install the fence and swale while doing the
adjacent field construction.
2. Dedicating a wetland-buffer easement. This easement shall describe the boundary of the
buffer and prohibit any building, mowing, cutting, filling or dumping within the buffer.
The applicant shall record the deed for this easement before the City will issue a
grading permit for the next phase of field reconstruction.
3. Accepting responsibility for any necessary maintenance and upkeep of the fence, swales
and ponding areas.
Seconded by Councilmember Carlson
Ayes - all
Councilmember Koppen introduced the following Resolution and moved its adoption:
98 -05 - 39
RESOLUTION CONDITIONAL USE PERMIT - HILL MURP~AY HIGH SCHOOL
WHEREAS, Hill-Murray High School requested that the City revise their conditional use permit
for a school and related athletic fields.
WHEREAS, this permit applies to 2625 Larpenteur Avenue East. The legal description is:
Part of the S N of the SE 1/4 of S 13, T 29N, R22W, Ramsey County, MN
WHEREAS, the history Of this conditional use permit is as follows:
1. On April 20. 1998, the Planning Commission recommended that the City Council approve
this revised permit.
2. The City Council held a public hearing on May 11, 1998. City staff published a notice
in the paper and sent notices to the surrounding property owners as required by law.
The Council gave everyone at the hearing a chance to speak and present written
statements. The Council also considered reports and recommendations of the City staff
and Planning Commission.
NOW. THEREFORE. BE IT RESOLVED that the City Council approve the above-described
conditional use permit revision, because:
I The use would be located, designed, maintained, constructed and operated to be in conformity with the City's comprehensive plan and Code of Ordinances.
2 The use would not change the existing or planned character of the surrounding area.
3 The use would not depreciate property values.
15
The use would not involve any activity, process, materials, equipment or methods of
operation that would be dangerous, hazardous, detrimental, disturbing or cause a
nuisance to any person or property, because of excessive noise, glare, smoke, dust.
odor. fumes, water or air pollution, drainage, water runoff, vibration, general
unsightliness, electrical interference or other nuisances.
The use would generate only minimal vehicular traffic on local streets and would not
create traffic congestion or unsafe access on existing or proposed streets.
The use would be served by adequate public facilities and services, including streets,
police and fire protection, drainage structures, water and sewer systems, schools and
parks.
The use would not create excessive additional costs for public facilities or services.
The use would maximize the preservation of and incorporate the site's natural and scenic
features into the development design.
9. The use would cause minimal adverse environmental effects.
lO.The City Council may waive any of the above requirements for a public building or
utility structure, provided the Council shall first make a determination that the
balancing of publ!c interest between governmental units of the state would be best
served by sucn waiver.
Approval is subject to the following conditions:
1. All construction shall follow the site plan and grading plan approved by the City. date-
stamped March 6, 1998. The Director of Community Development may approve minor changes.
The school shall move the proposed temporary storage buildings as far away from the
wetland buffer as possible to minimize the variance they will need.
2. The City Council shall review this permit annually to monitor the traffic and parking
situations related to the use of the athletic fields.
o
o
Any new lights shall be installed to meet the City Code. This requires that they be
screened or aimed so they do not cause any light-glare problems on streets or
residential properties.
Dedicate and record a wetland-protection buffer easement. This easement shall describe
the boundary of the buffer and prohibit any building, mowing, cutting, filling or
dumping within the buffer. The buffer shall follow the proposed chain-link fence line
on' the plans date:stamped March 6, 1998. The part of this wetland buffer area that is
already mowed lawn may remain as such. The school shall have the contractor install the
fence and swale while doing the adjacent field construction.
Post signs on the edge of the wetland-protection buffer prohibiting any building,
mowing, cutting, filling or dumping within the buffer. Wetland buffer signs in the
mowed area shall be placed at the edge of the lawn.
That portion of the proposed walking/running path that is within 50 feet of the wetland
shall be built with a pervious material.
Ensure that all bleachers and dugouts are at least 30 feet from the Sterling Street and
Larpenteur Avenue right-of-ways.
The City may require the applicant to plant 30 native species of trees for screening
between the playing fields and the homes on Knoll Circle. as may be determined at a
future hearing on the Conditional Use Permit.
The school shall prepare for City approval a turf management plan for the athletic
fields. This plan shall include the mowing watering and fertilizing practices that the
school will follow in the care of their athletic fields and grounds. The school shall
prepare and follow the plan so the practices will minimize the impact of the storm water
runoff on the nearby wetlands.
16
lO.Submit a grading and drainage plan for watershed d~strict approval to provide
sedimentation control at the storm water discharge point before it dumps into the south
wetland area.
Seconded by Councilmember Carlson.
Ayes - all
17
CONDITIONAL USE PERMIT REVISION RESOLUTION
WHEREAS, Hill-Murray High School requested that the city revise their conditional use permit
for a school.
WHEREAS, this permit applies to 2625 Larpenteur Avenue East. The legal description is:
Part of the S % of the SE 1/4 of S 13, T 29N, R22W, Ramsey County, MN (PIN 13-29-22-43-
0001)
WHEREAS, the history of this conditional use permit is as follows:
1. On June 7, 1999, the planning commission recommended that the city council approve
this revised permit.
The city council held a public hearing on ,1999. City staff published a notice in
the paper and sent notices to the surrounding property owners as required by law. The
council gave everyone at the hearing a chance to speak and present written statements.
The council also considered reports and recommendations of the city staff and planning
commission.
NOW, THEREFORE, BE IT RESOLVED that the city council approve the above-described
conditional use permit revision, because:
1. The use would be located, designed, maintained, constructed and operated to be in
conformity with the city's comprehensive plan and code of ordinances.
2. The use would not change the existing or planned character of the surrounding area.
3. The use would not depreciate property values.
The use would not involve any activity, process, materials, equipment or methods of
operation that would be dangerous, hazardous, detrimental, disturbing or cause a
nuisance to any person or property, because of excessive noise, glare, smoke, dust, odor,
fumes, water or air pollution, drainage, water runoff, vibration, general unsightliness,
electrical interference or other nuisances.
5. The use would generate only minimal vehicular traffic on local streets and would not
create traffic congestion or unsafe access on existing or proposed streets.
The use would be served by adequate public facilities and services, including streets,
police and fire protection, drainage structures, water and sewer systems, schools and
parks.
7. The use would not create excessive additional costs for public facilities or services.
8. The use would maximize the preservation of and incorporate the site's natural and scenic
features into the development design.
9. The use would cause minimal adverse environmental effects.
3.8
10.
The city council may waive any of the above requirements for a public building or utility
structure, provided the council shall first make a determination that the balancing of public
interest between governmental units of the state would be best served by such waiver.
Approval is subject to the following conditions:
1. All construction shall follow the plans as noted below:
a. For the athletic fields, follow the plans date-stamped March 6, 1998.
b. For the school and entry addition, follow the plans date-stamped May 6, 1999.
The director of community development may approve minor changes. The school shall
move the proposed temporary storage buildings as far away from the wetland buffer as
possible to minimize the variance they will need.
The proposed construction for the front entry addition and drop-off drive must be
substantially started within one year of council approval or the permit revision shall end.
The council may extend this deadline for one year.
3. The city council shall review this permit annually to monitor the traffic and parking
situations related to the use of the athletic fields.
Any new lights shall be installed to meet the city code. This requires that they be screened
or aimed so they do not cause any light-glare problems on streets or residential
properties.
Dedicate and record a wetland-protection buffer easement. This easement shall describe
the boundary of the buffer and prohibit any building, mowing, cuffing, filling or dumping
within the buffer. The buffer shall follow the proposed chain-link fence line on the plans
for the athletic fields date-stamped March 6, 1998. The part of this wetland buffer area
that is already mowed lawn may remain as such. The school shall have the contractor
install the fence and swale while doing the adjacent field construction.
Post signs on the edge of the wetland-protection buffer prohibiting any building, mowing,
cutting, filling or dumping within the buffer. Wetland buffer signs in the mowed area shall
be placed at the edge of the lawn.
7. That portion of the proposed walking/running path that is within 50 feet of the wetland
shall be built with a pervious material.
8. Ensure that all bleachers and dugouts are at least 30 feet from the Sterling Street and
Larpenteur Avenue right-of-ways.
The city may require the applicant to plant 30 native species of trees for screening
between the playing fields and the homes on Knoll Circle, as may be determined at a
future hearing on the Conditional Use Permit.
10.
The school shall prepare for city approval a turf management plan for the athletic fields.
This plan shall include the mowing, watering and fertilizing practices that the school will
follow in the care of their athletic fields and grounds. The school shall prepare and follow
the plan so the practices will minimize the impact of the storm water runoff on the nearby
3.9
wetlands. The city must approve this plan before issuing a building permit for the front-
entry addition.
11.
Submit a grading and drainage plan for watershed district approval to provide
sedimentation control at the stormwater discharge point before it dumps into the south
wetland area.
The Maplewood City Council approved this resolution on
,1999.