HomeMy WebLinkAbout2013-09-24 CDRB Packet
AGENDA
CITY OF MAPLEWOOD
COMMUNITY DESIGN REVIEW BOARD
Tuesday, September 24, 2013
6:00 P.M.
Council Chambers -Maplewood City Hall
1830 County Road B East
1.Call to Order
2.Roll Call
3.Approval of Agenda
4.Approval of Minutes:
a.August 27,2013
5. Unfinished Business:
6.Design Review:
a.Approval of Design Review Revisions for CarMax, Highway 61 and Beam Avenue
b.Approval of a Design Review and Parking Waiver for Maplewood Fire Station No. 1,
McKnight Road
7.Visitor Presentations:
8.Board Presentations:
9.Staff Presentations:
10.Adjourn
DRAFT
MINUTES OF THE MAPLEWOOD COMMUNITY DESIGN REVIEW BOARD
1830 COUNTY ROAD B EAST, MAPLEWOOD, MINNESOTA
TUESDAY, AUGUST 27, 2013
1.CALL TO ORDER
Chairperson Ledvinacalled the meeting to order at6:00p.m.
2.ROLL CALL
Boardmember, Leo BurgerPresent
Boardmember, Bill KempePresent
Boardmember,Jason LamersPresent
Chairperson,Matt LedvinaPresent
Boardmember,Ananth ShankarPresent
Staff Present:
Michael Martin, Planner
3.APPROVAL OF AGENDA
BoardmemberKempemoved to approve the agenda assubmitted.
Seconded by BoardmemberLamers.Ayes -All
The motion passed.
4.APPROVAL OF MINUTES
BoardmemberShankarmoved to approve the July 23, 2013,CDRB minutes as submitted.
Seconded by BoardmemberBurger.Ayes –Chairperson Ledvina,
Boardmember Burger
& Shankar
Abstentions –Boardmember’s Kempe
& Lamers
The motion passed.
5.UNFINISHED BUSINESS
None
6.DESIGN REVIEW
a.Approval of Design Review for Exterior Remodel, Kohl’s, 3001 White Bear Avenue
i.Planner, Mike Martin gave the report and answered questions of the board.
ii.Kohl’s representativeAdam Stein addressed and answered questions of the board.
August 27, 2013
Community Design Review Board Meeting Minutes
1
BoardmemberLamersmoved to approvethe design plans date-stamped August 6, 2013, for
exterior remodeling andthe sign relocation proposal for Kohl’s at the Maplewood Mall.
Seconded by BoardmemberBurger.Ayes –All
The motion passed.
b.Approval of Design Review for Tennis Court Addition, Hill Murray School, 2625
Larpenteur Avenue
i.Planner, Mike Martin gave the report and answered questions of the board.
ii.Larry Wacker, with Sanders Wacker Bergly, representing Hill Murrayaddressed and
answered questions of the boardand gave a brief presentation.
BoardmemberShankar moved to approvethe project plans date-stamped July 29, 2013, (site
plan, landscape plan, grading and drainage plans and elevations) for the tennis court complex
addition at Hill Murray School at 2625 Larpenteur Avenue. The city bases this approval on the
findings required by the code. The developer or contractor shall do the following:
1.Repeat this review in two years if the city has not issued a building permit for this project.
2.Complete the following before the city issues a building permit:
a.Have the city engineer approve final construction andengineering plans. These plans
shall include: grading, utility, drainage, erosion control, tree and sidewalk plans. The
plans shall meet all the conditions and changes noted in Jon Jarosch’s memo dated
August 1, 2013, and in Ginny Gaynor’s memo dated August 6, 2013.
b.Provide the city with a letter of credit or cash escrow for all required exterior
improvements. The amount shall be 150 percent of the cost of the work.
3.Complete the following before occupying the addition:
a.Replace property irons that areremoved because of this construction.
b.Restore and sod damaged turf areas.
c.Complete all landscaping for the addition.
d.Install and maintain all required trees and landscaping (including the plantings around the
pond) and an in-ground sprinkler system forall landscaped areas (code requirement).
4.If any required work is not done, the city may allow temporary occupancy if:
a.The city determines that the work is not essential to the public health, safety or welfare.
b.The above-required letter of credit or cash escrow is held by the city for all required
exterior improvements. The owner or contractor shall complete any unfinished
landscaping by June 1 of the next year if the building is occupied in the fall or winteror
within six weeks of occupancy if the building is occupied in the spring or summer.
August 27, 2013
Community Design Review Board Meeting Minutes
2
5.All work shall follow the approved plans. The director of community development may
approve minor changes.
Seconded by BoardmemberLamers.Ayes –All
The motion passed.
c.Approval of Design Review and Parking Waiver for Lab and Office Building, 3M
Company, McKnight Road and Conway Avenue
i.Planner, Mike Martin gave the reportand answered questions of the board.
ii.Roger Spinner, 3M addressed the board.
iii.Jim DavyBWBR Architect, Chuck Evens, Landscaping DesignwithDamon Farber
Associates, Darren Schwankl, Civil Engineer, TKDA addressed and answered questions
of the boardregarding the 3M project.
Boardmember Lamersmoved to approvethe plans date-stamped August 12, 2013, for the
proposed 3M Company Research Building. Approval is based on the findings for approval
required by ordinance and subject to the developer doing the following:
1.Repeat this review in two years if the applicant has not obtained a building permit by that
time. After two years this review mustbe repeated.
2.Comply with the requirements in the Engineering Plan Review by Michael Thompson, the
Environmental Plan Reviewby ShannFinwall and those of the Assistant Fire Chief,
Building Official and Lieutenant Doblar.
3.Submit a revised landscape plan for staff approval for additional landscaping along
Conway Avenue and McKnight Road.
4.Before obtaining a building permit, the applicant shall provide an irrevocable letter of credit
in the amount of 150 percent of the cost of completing landscaping and other site
improvements. This irrevocable letter of credit shall include the following provisions:
The letter of credit must clearly indicate that it is an irrevocable letter of credit in the
name of the City of Maplewood, payable on demand, to assure compliance with the
terms of the developer’s agreement.
The letter of credit must allow for partial withdrawals as needed to guarantee partial
project payments covered under the terms of the letter of credit.
The letter of credit shall be for a one-yearduration and must have a condition
indicating automatic renewal, with notification to the city a minimum of 60 days prior to
its expiration.
5.All landscaped areas shall have a lawn-irrigation system installed, except for those areas
proposed to be left natural. The applicant must, however, make sure to use hoses and
sprinklers until turf, plant and tree growth is established.
6.If outdoor trash storage is used in the future, the applicant shall provide a screening
enclosure that is compatible in design with the building.
August 27, 2013
Community Design Review Board Meeting Minutes
3
7.Any proposed signs shall comply with the comprehensive sign plan and shall be submitted
for approval by the community design review board.
8.The applicant must submit a summary of how the site is meeting the city’s volume
reduction requirements in order to qualify for the 11 percent impervious surface area
bonus. The bonus shall be approved by the city engineer based on the installation and
maintenance of manmade facilities for reducing stormwater flow or the treatment or runoff
for non-point-source water pollutants.
9.The applicant must submit the following information in order to determine if the site meets
the city’s tree preservation ordinance:
a.Tree inventory which includes all significant trees located on the site (not just the
developed area) and the size and number of significant trees removed with the
development.
b.Planting schedule which shows the tree species, tree size, and number of each
species being replaced on the site.
10.All work shall follow the approved plans. Staff may approve minor changes.
11.Submit for staff approval, the color chosen for glass wall and a site plan indicating any
visitor parking, if provided.
B.Approve a parking waiver to allow for 580 surface parking spaces. The parking spaces shall
be at least 9.5 feet in width. This is a parking reduction of 1,420 parking spaces (2,000
parking spaces are required per city code).
Seconded by BoardmemberKempe.Ayes –Chairperson Ledvina,
Boardmember’s Burger,
Kempe & Lamers
Abstention–Boardmember Shankar
The motion passed.
Boardmember Shankar abstained from the vote because he is on the design team for 3M.
7.VISITOR PRESENTATIONS
None
8.BOARDPRESENTATIONS
Staff requested a board representative for the September 9, 2013, City Council meeting.
Boardmember Shankar stated he could represent theCDRB.
9.STAFF PRESENTATIONS
None.
August 27, 2013
Community Design Review Board Meeting Minutes
4
10.ADJOURNMENT
The meeting was adjourned by Chairperson Ledvinaat7:14p.m.
August 27, 2013
Community Design Review Board Meeting Minutes
5
MEMORANDUM
TO:CharlesAhl, City Manager
FROM:Michael Martin, AICP, Planner
DATE:September 18,2013
Approval of Design ReviewRevisionsforCarMax, Highway 61 and
SUBJECT:
Beam Avenue
Introduction
Request
CarMax Auto Superstoreis requesting approval of their design reviewrevisions for itsproposed
auto dealership at the northeast corner of Highway 61 and Beam Avenue. The community
design review board approved the original plans on December 12, 2006.Refer to the
applicant’s narrative and plans.
Project Description
The proposed project will include an 11,645 square foot sales building with an attached 2,167
square footpresentation area and 6,506 square footservice area as wellas a detached 923
square foot non-public carwash. The site is currently undeveloped.
Background
December 12, 2006: The community design review board (CDRB) approved the CarMax plans,
which were submitted to the city council for their review as well.
December 18, 2006: The city council approved a conditional use permit (CUP) for a planned
unit development (PUD), the preliminary plat and moved to have the CDRB review the design
revisions discussed at the council meeting.The council also adopted a resolution ordering the
public improvements for the CarMax/Mogren Addition.
January 9, 2007: The CDRB approved the revisions to the building elevations.
February 12, 2007: The city council approved the final plat.
Discussion
Architectural
CarMax’s approved design plans from 2006 and 2007 incorporated the use of a brick surface
and EIFS. The current proposed designs of the CarMax buildings would be somewhat lacking
in terms of both material selection and design. Theelevations for this proposed projectwould
have four highly-visible views. The primary building material in each of these views would be a
combination of smooth and split-face block.
Staff voicedits concern to the applicant regarding the use of concrete blocks and stated the use
of brick face would be more appropriate. The applicant did respond to staff’s concerns
regarding the use of concrete blocks and agreed to use brick in accordance to the original 2006
and 2007 approvals. Staff is recommendingrevised building elevations be submitted for staff
approval.
Site Plan
The applicant is proposing a singlecurb cut on Beam Avenue.Thiswould allow right and left
turns into the site and right-turn exits only. The parking lot would meet the minimum 15 foot
setback. The building setback is 30 feet from any right-of-way, which the applicant has also
met.
Parking Requirements
CarMax received approval from the city council in 2006, as part of the planned unit development
request, which allows the applicantto have 9-foot-wide parking stalls in their “inventory parking”
area. City ordinance does not have a parking requirement for inventory parking and these
smaller spaces would merely create tighter parking stalls for the CarMax vehicle inventory.
Auto dealers typically provide smaller spaces for their vehicle inventory.
The applicant is proposing to have customer and employee parking meet ordinance
requirements for dimensions. All spaces will be 9.5 feet wide and 20 feet deep, with 24 foot
drive aisles. City ordinance would require 102 parking spaces, based on the proposed building
size. The applicant is proposing to provide 201 parking spaces, which does not include any of
the inventory parking.
Carwash and Staging Area
The location of the staging area and carwash remain north of the proposedbuildings and is
shown in two development phases. Phase 1 includes a staging area of 1.37 acres and a single
bay Carwash. Phase 2, if CarMax chooses to expand, would create an expanded staging area
of approximately 0.86 acres and a three bay carwash/quality control building. Upon full build-out
of the site, the staging area wouldextend from the building up to County Rd D. The applicant is
proposingasix-foot masonry wall surrounding the staging area.The 2006and 2007 approvals
required this wall to at least have brick showing on the outward facing side of the wall.
Shoreland Ordinance
The southwest corner of the CarMax site is within the Kohlman Lake Shoreland Boundary Area.
The City’s Shoreland Ordinance allows for a maximum of 30 percent impervious surface
coverage for a lot located within this District, and up to 50 percent impervious surface coverage
with bonuses. The city engineer shall determine whether bonuses are allowed based on the
installation and maintenance of manmade facilities for reducing stormwater flow or the treatment
of runoff for non-point-source water pollutants.
The applicant proposes 26,683 square feet of porous paving to comply with the pervious
pavement requirements. With the pervious pavement and minimal green space required with
the parking lot setback and landscaping adjacent the boulevard, the applicant’s site plan shows
57 percent (50,488 square feet) of impervious surface area within the Kohlman Lake Shoreland
District boundary. This is 7 percent over the allowable 50 percent impervious surfaceallowed
with bonuses.The applicant must submit a revised plan which shows an increase of 8,200
square feet of bituminous porous pavement in order to maintain a maximum of 50 percent
impervious surface coverage within the Shoreland District.
Landscaping
Theoveralllandscaping plan is attractive.There are opportunities along Beam Avenue and
Highway 61 to add more trees, where there are currently a few gaps. The plan does show
areas where the applicant is proposing to seed for grass instead of usingturf. The applicant will
be grading into portions of the right-of-way and the code does not allow this area to be restored
with seed, turf must be used. Staff is also concerned about the use of seed in other places
throughout the site, given the location within the shoreland overlay and its proximity to wetlands.
Staff feels turf would be a more appropriate method of restoration than relying on seed.
Tree Preservation
The applicant’s landscape plan shows a total of 161 replacement trees (including 111 –2.5
caliper inch deciduous trees, 24 ornamental trees, and 31 8-foot high evergreen trees). This
equals 404 caliper inches of replacement trees, which does not meet the original Planned Unit
Developmenttree replacement requirement of 523 caliper inches.
The applicant must submit a revised landscape plan showing an additional 119 caliper inches of
trees to be planted on the site. This can be accomplished by adding trees to the site or
increasing the size of the replacement trees.
Site Lights
The lighting plan indicates a heavily-lit site. The lighting plan does show areas where the
ordinance maximum of 0.4 footcandles is exceeded. Staff recommends a revised plan be
submitted showing a repositions of the light poles so the ordinancerequirements are met. Care
should be taken so that site lights, either building mounted or pole mounted, do not shine
outward.
Department Comments
BuildingOfficial’s Comments
Dave Fisher, the Maplewood Building Official, had these comments:
The city will require a complete building code analysis when the construction plans are
submitted to the city for building permits.
A separate building permit is required for each building.
All exiting must go to a public way.
Provide adequate fire department access to the buildings.
The buildings are required to be fire sprinklered.
I would recommend a pre-construction meeting with the contractor, the project manager and
the city building inspection department.
Fire Marshal’s Comments
Butch Gervais, the Maplewood Fire Marshal, had these comments/requirements:
Need 20-foot emergency access road at all times.
Fire protection system per codes and monitored.
Fire alarm system per code and monitored.
Fire department lockbox required. Get the paperwork from the fire marshal.
There must be proper protection for any tanks stored above ground.
The applicant must get proper permits for any tanks installed above or below ground.
Police Department Comments
Police Chief Paul P. Schnellhas reviewed the plans and has no concerns.
Engineering Comments
Please see Jon Jarosch and Ron Leaf’sreports, attached to this memo.
EnvironmentalComments
Please see Shann Finwall and Virginia Gaynor’sreport, attached to this memo.
Recommendations
Approve the plans date-stamped September 4,2013, for the proposed CarMax Automobile
Superstore. Approval is subject to the developer complying with the following conditions:
1.This approval is good for two years. After two years, the design-review process shall
be repeated if the developer has not begun construction.
2.All requirements of the fire marshal and building official must be met.
3.The applicantsshall obtain all required permits from the Ramsey-Washington Metro
Watershed District and Ramsey County.
4.The building elevations shall be revised and resubmitted to stafffor approval. The
proposed buildings shall not have smooth-face concrete block. The applicantsshall
utilizebrick and more decorative materials and apply decorative architectural features
to improve the appearance of both buildings.
5.The design of the six-foot-tall screening wall must be submitted to stafffor approval.
The wall shall have brick showing on the outward facing side.
6.The landscaping plan shall be resubmitted for staff approval showing the following
revisions:
A.Plan shall show more extensive landscaping along all right-of-way frontages.
B.Plan shall also meet the tree preservation requirements.
C.Plan shall show areas within right-of-way and near the wetlands and rain gardens
being restored with sod,not seed.
7.The applicant shall submit a revised lighting plan for staff approval. The revised plan
shall show the applicant meeting the 0.4 footcandle standard at all property lines.
8.All driveways and parking lots shall have continuous concrete curbing.
9.The applicant shall comply with all requirements of the Maplewood Engineering Report
from Jon Jarosch dated September 17, 2013.
10.The applicant shall comply with all requirements of the Maplewood Engineering Report
from Ron Leafdated September 10, 2013.
11.The applicantshall comply with all requirements of the Maplewood Environmental
Report from Shann Finwalldated September 17, 2013.
12.The applicants shall:
A.Install reflectorized stop signs at the proposed exits onto Beam Avenue.
B.Install and maintain an in-ground lawn irrigation system for all landscaped areas.
13.The applicantsshall provide the city with cash escrow or an irrevocable letter of credit
for the exterior landscaping and site improvements prior to getting a building permit for
the development. Staff shall determine the dollar amount of the escrow.
14.All work shall follow the approved plans. The director of community development may
approve minor changes.
15.All roof-top mechanical equipment shall be painted to match the building.
Reference
Site Description
Site Size:12.4acres
Existing Use:Undeveloped
Surrounding Land Uses
North:County Road D Extension and Lexus ofMaplewood
South:Beam Avenue and wetlands
East:An undeveloped commercial property and Costco
West:Highway 61, Maplewood Toyota and LaMettry Collision
Planning
Land Use Plan Designation: C(commercial)
Zoning: PUD
Application Date
Staffreceived the complete applications and plans for these requests onSeptember 4,2013.
State law requires that the city take action within 60 days of receiving complete applications for
a proposal. City action is required on this proposal by November 4, 2013.
Attachments
1.Location Map
2.Aerial Site Map
3.Entire-Project Site Plan
4.Landscaping Plan
5.Building Elevations, 2013
6.Building Elevations, 2006
7.Applicant’s Narrativedated September 3, 2013
8.Engineering Report from Jon Jarosch,dated September 17,2013
9.Engineering Report from Ron Leaf,dated September 10,2013
10.Environmental Report from Shann Finwall, dated September 17, 2013
11.Community Design Review Board Minutes, dated December 12, 2006
12.Community Design Review Board Minutes, dated January 9, 2007
13.Plans date-stamped September 4,2013 (separate attachments)
p:sec 3\CarMax Resubmittal 2013\CarMax Design Revisions_CDRB_092413
Attachment 1
Costco
CarMax
Proposed CarMax
Location Map
Attachment 2
CarMax
Proposed CarMax
Aerial Site Map
Attachment 4
Attachment 5
Attachment 5
Attachment 5
Attachment 6
Attachment 6
Attachment 7
September 3, 2013
City of Maplewood
Attn: Tom Ekstrand
1830 County Rd B East
Maplewood, MN 55109
Re: Site Narrative for the CarMax Maplewood Site Development – CDRB Application
Dear Tom:
This letter is to serve as an overview of the CarMax Maplewood development plan for consideration by
the City of Maplewood staff and the Community Design Review Board. The CarMax development is
located on the northeast corner of Beam Avenue and US Highway 61. The attached revised plan will
allow CarMax to develop the property consistent with the intent of the previously approved plan from
2007. We believe these revisions are minor and that the overall site will function very much the same as
the previous plan approved in 2007.
Proposed Development:
The proposed development consists of the construction of a CarMax pre-owned automobile dealership,
service building and non-public carwash with associated access drives, parking lots and landscaped
areas. The site is currently undeveloped. The proposed project will include a 11,645 sf sales building
with an attached 2,167 sf presentation area, and 6506 sf service area as well as a detached 923 sf non-
public carwash. More detail on the site layout and an overview of revisions from the 2007 approved plan
are discussed in the table below.
Hours of Operation
Store management will set operating hours closer to the opening date; however, the showroom (sales)
areas are typically open to the public Monday through Saturday from 9:00 a.m. to 9:00 p.m. with limited
hours on Sundays, if permitted by local law. The retail service areas are typically open to the public
Monday through Friday from 7:30 a.m. to 6:00 p.m. Associates will be present at the store several hours
before and after the public operating hours.
Deliveries of vehicles, parts and supplies are made on-site and typically require the presence of
associates to receive the delivery. Vehicle carriers will enter the site through the main access on Beam
Ave and load and unload vehicles towards the rear of the customer and employee parking lot. Unloaded
vehicles will be driven by employees from the parking lot into the staging area to await preparation for
resale.
Sales & Marketing
CarMax operates differently from traditional car dealerships in that it physically separates its inventory
area from customer and employee parking. This is both for loss prevention control as well as operational
efficiency and safety. All inventory display areas will be separated from the general public by means of
highway guardrail, gates, and fencing. Ornamental wrought-iron fencing is used to separate the
customer and employee parking from the display area.
1240 Bergen Pkwy | Suite A-250 | Evergreen, CO 80439 | 303.670.4111 | Fax: 877.736.9960
www.centerpoint-is.com
Attachment 7
CarMax Maplewood Plan Revisions
September 3, 2013
Vehicular access to the display areas is controlled by embassy-style security gates through the use of a
secured key-card. Prospective customers are typically accompanied by an employee when they are in
the display area. Only employees are permitted to drive cars within the display area. Emergency access
will be provided within staging and display area as required by the local fire department.
CarMax does not use outdoor loudspeakers as associates carry pagers and / or cell phones for
communications. In addition, CarMax does not use flags, balloons, inflatable gorillas (or any other
animal), placards in open car hoods, painted window lettering or the like in its marketing. Instead, they
promote a high-end retail operation, and a welcoming environment to their customers and associates.
Service Operations
An integral part of the CarMax used car consumer offer is the reconditioning process that is performed
on all vehicles offered for sale. This process includes a comprehensive Certified Quality Inspection of the
engine and all major systems. Most routine mechanical and cosmetic repairs required to bring the
vehicle up to the CarMax quality standards are performed in house; however, for some reconditioning
services, third parties specializing in those services are engaged.
CarMax currently offers limited retail vehicle service (routine maintenance, tires, diagnostic, and
mileage services) and provides repairs of vehicles covered by their extended service plans. All service
work is performed inside fully-conditioned buildings equipped with rollup doors, providing the
associates with a great work environment and eliminating the need to conduct operations with open
bay doors.
Retail service vehicles and vehicles awaiting disposition off-site are stored in the secured non-public
staging area on a temporary basis. As a visual screen and to provide security for these vehicles, the
staging area is surrounded by a six foot high masonry wall. Vehicular access to that area is strictly
controlled through the use of embassy-style security gates. Because the staging and storage of vehicles
within this area is constantly changing on a daily basis, parking spaces are not designated on the plan.
The non-public carwash is located in the secured staging area and is used only by CarMax associates
before vehicles are either placed in the vehicle display area or presented to customers.
An above ground fuel storage tank with a non-public fuel pump is proposed for this site. The tank and
fuel pump will be located adjacent to the carwash within the secured staging area to fuel inventory
vehicles as needed.
Site Lighting & Security
CarMax uses “shoebox” type lighting fixtures mounted on 26-foot tall light poles for visibility and
security. Fixture heads are full cut-off shoe box style heads that use a flat lens. Lighting is downcast to
reduce light spill onto adjacent properties. Exterior lighting will be reduced after operating hours.
CarMax typically does not use on-site security guards, but uses interior and exterior security cameras for
safety and inventory protection
Proposed Revisions
The following table lays out major components of the site plan and any revisions that have been
proposed from what was approved in 2007. It is important to note that the development boundaries of
the plan have not been changed from the original plan approved in 2007. Setbacks to US Highway 61
and Beam Avenue also remain unchanged, as are the setbacks to the wetland and watershed areas.
2
Attachment 7
CarMax Maplewood Plan Revisions
September 3, 2013
Site Plan ComponentProposed Changes
Sales/PresentationBuildingThe orientation of the sales building and presentation area remains
Orientation the same with customer entrance and exit on the south and west
sides of the building.
Service BuildingOrientationThe general location of the service building remainsthe same (north
of the Sales/Presentation buildings)
Carwash and Staging AreaThe general location of the Staging Area and Carwash remain north
Orientation of the service/sales/presentation buildings, and is now shown in two
development phases. Phase 1 includes a staging area of 1.37 acres
and a single bay Carwash. Phase 2, if CarMax chooses to expand,
would create an expanded staging area of approximately 0.86 acres
and a three bay carwash/quality control building. Upon full build-out
of the site, the staging area would extend from the building up to
County Rd D and is anticipated to have a 6’ masonry wall
surrounding the area.
SalesDisplayAreaOrientationThe Sales Display Area remains along the western boundary of the
property extending north from the corner of Beam Ave and US 61.
The proposed plan also reflects the full build-out of the sales area in
two phases. Phase 1 would be approximately 2.53 acres of Sales
Display Area from Beam Ave. north toward County Rd D along US 61.
Phase 2, if CarMax chooses to expand, would include the extension
of the Sales Display Area north to the property boundary along
County Rd D for a total of approximately 0.29 acres.
Customer/Employee ParkingThe Customer/Employee Parking area is consistent with the
requirements of the 2007 plan, reflecting 9.5’x20’ parking spaces
with 24’ drive aisles. As described below, the customer/employee
parking lot is the location of the pervious surface required by the
Shoreland Overlay District.
Access and CirculationAccess to the site is off Beam Ave on the far east side of the
property. The original 2007 plan showed an additional access point
to the sales area from County Rd D. After the approval of the plan,
conversations held jointly with CarMax, the City of Maplewood, and
the County did not result in an approved access on County Rd D and
therefore the proposed plan does not reflect that access point.
Circulation internal to the site functions in a circular pattern.
Customers/Employees will enter the site off Beam Ave and park in
the C/E lot as indicated on the plan. There is a delta gate at the
southern end of the sales area into the C/E lot allowing access for
customers test driving vehicles. There is a second delta gate on the
south side of the staging area adjacent to the service building which
allows access to the rear of the building.
Shoreland Overlay District The proposed plan calculates the Shoreland Overlay District
Compliance requirements for pervious pavement consistent with the approved
2007 plan, which requires 43% pervious pavement. The proposed
plan reflects 43% (50,488 sf/117,415 sf)of the Shoreland Overland
District Area as pervious pavement contained in the
3
Attachment 7
CarMax Maplewood Plan Revisions
September 3, 2013
Customer/Employeelot.
Building SizeThe proposed plan shows a total building square footage of 21,241sf
in Phase 1 with a possible carwash/quality control building expansion
in Phase 2 of an additional 2,768 sf. Expansion of the carwash would
occur concurrently with the expanded sales and staging areas if
CarMax chooses to do so.
Tree Replacement and Treereplacement calculations were based off of correspondence
Landscaping Plan from Michael Thompson, City Engineer for the City of Maplewood, in
January of 2008 as well as email correspondence in August of 2012.
The landscape plan was designed to be closely representative of the
plan approved in 2007 to be consistent with past approvals.
As mentioned above, we believe these changes to be minor and that the spirit of the 2007 approval is
still consistent with the intent of the development plan moving forward. CarMax is excited about its
growth into the Twin Cities area and we look forward to working with you to get this project across the
finish line.
Sincerely,
Morgan Landers
CenterPoint Integrated Solutions, Inc.
Enclosed:Community Design Review Board application and submittal requirements
4
Attachment 8
Engineering Plan Review
PROJECT: CarMaxAuto Dealership
PROJECT NO: 13-11
SUBMITTAL NO: 4
REVIEWED BY: Jon Jarosch, Civil Engineer I
DATEOF REVEW:September 17, 2013
CarMax is ready to build at the corner of Highway 61 and Beam Avenue. They have made some
minor changes to the design approved in 2006. The developer shall address the following
questions and comments.
Stormwater
1.Please refer to the attached review performed by Ron Leaf, Senior Engineer with SEH,
Incorporated. All conditions noted in this report shall be addressed.
Miscellaneous
1.The developer or project engineer shall submit a copy of the MPCA’s construction
stormwater permit (SWPPP) to the city before the city will issue a grading permit.
2.The proposed water service shall be reviewed and approved by Saint Paul Regional
Water Services. A copy of a letter confirming their approval of the proposed service shall
be submitted to the City prior to the issuance of a grading permit.
3.The developer shall meet all requirements set forthin thesigned Development
Agreement(s) for this project.
4.The owner and project engineer shall satisfy the requirements of all permitting agencies.
5.The owner shall sign a maintenance agreement, prepared by the city, for all stormwater
treatment devices (list devices i.e.…sumps, basins, ponds, etc). The city shall prepare
this agreement upon plan approval.
6.The developer shall pay all permit fees, escrows, and charges (SAC, WAC, PAC)
associated with this project prior to permit issuance. The developer shall work with the
Parks Director in regards to the PAC fee.
Attachment 9
MEMORANDUM
TO:Steve Love, PE,PLS
Assistant City Engineer, City of Maplewood
FROM:Ron Leaf, PE | Principal
Sr. Water Resources Engineer, SEH
DATE:September 10, 2013
RE:Carmax - Review of August 2013 Stormwater Analysis and Plan Submittal
SEH has completed a review of the following information provided by the City and relating to the proposed Carmax
Development on TH 61 and Beam Avenue in Maplewood, MN:
Stormwater Analysis, August30, 2013.Westwood Professional services, Inc. (Westwood)
Preliminary Plans, September 3, 2013. Westwood.
The goal of this review was to evaluate the general conformance of the proposed stormwater system with City
standards for treatment and rate controls,and to the existing system analysis presented in the 2010 Stormwater and
Wetland System Report for the MMATI Project Area (SEH, November 2010).Our comments/questions are:
1.Check the impervious/pervious summary on page 1 in the Project Description section of the Stormwater
Report. The areas are listed wrong in the pervious and impervious lines for the proposed conditions.This
appears to be the only location where the impervious area is listed incorrectly.
2.An exfiltration rate of 1.0 in/hr is used in HydroCADmodeling for the filtration basins. Note thatthe
RWMWD worksheet usesa maximum value of0.8 in/hr for filtration systems.We recommend that this
value be updated. It does not appear that this change will impact maximum ponding depths in any of the
filtration/rain water garden areas (i.e., maintaining a maximum 48 hour drawdown time).
3.Rain garden soil filtration media volumes appear to assume vertical sidewalls excavated below the surface
outlet invert elevation instead of the bottom of each RG (for example at elevation 871 instead of 872 for
RG #1). A40% voids is used in the filtration soils for volume reduction credit calculations.We believe this
value is too high for the soil media. We typically assume 30% voids. The 40% value is reasonable for the
porous pavement section.
4.Notes specify completion of infiltration test by contractor prior to placement of plants in basins. Please add
a note that requires notification of the City and RWMWD at least 2 days in advance of this testing. Is there
a specific test method that you will require the contractor to use?
5.Planting media soil specifies 70% sand with 5% passing the #200 sieveand 30% organic.We would
generally recommend clean washed sand to further limit the fine material. Should this item be read as a
maximum 5% passing the 200 sieve?
6.Will drain tile systems have a cleanout? We suggest adding a cleanout detailand a temporary overflow at a
depth of less than 1.0 footto allow the basins to drain down faster during theplant establishment period
(i.e., will the newly planted plants be able to withstand up to 1+ foot of inundation for expected draw down
time in each basin)?
7.Sheets C4 and C5 show the general routing of stormwaterinto the rain gardens through direct runoff or
storm sewer. The plans do not appear to show any pretreatment devices (e.g., sump manholes,
Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196
SEH is an equal opportunity employer | www.sehinc.com | 651.490.2000 | 800.325.2055 | 888.908.8166 fax
Carmax – 2013 Submittal Review
September 10, 2013
Page 2
RainGuardian, etc.) to capture sediment and gross solids/debris priorto discharge into the rain water
gardens. Someform of pretreatment must be provided.
8.Rate control. Rate controls appear to be consistent with the previous submittals and the information
available in the 2010 Stormwater and Wetland System Report for theMMATI Project Area report.
9.The EOF elevation forpond “PR Pond” is not designated on the plans and is not identified in the
HydroCAD modeling summary. As it is currently graded, it appears that the EOF could go to the east into
the existing wetland system. Please revise/clarify that EOF routes to the south to Beam Avenue.
Attachment 10
Environmental Review
Project:
CarMaxAuto Superstore
Dateof Plans:
September 3, 2013
Date of Review:
September 16, 2013
Location:
Northeast Corner of Beam Avenue and Highway 61
Reviewers:
Shann Finwall, Environmental Planner
(651) 249-2304; shann.finwall@ci.maplewood.mn.us
Ginny Gaynor, Natural Resources Coordinator
(651) 249-2416, virginia.gaynor@ci.maplewood.mn.us
Background:
CarMax Auto Superstore is proposing to construct an auto dealership at
the northeast corner of Highway 61 and Beam Avenue. The development is located
within the Mogren Addition plat, which was approved by the City in 2006 and 2007. The
plat included a Planned Unit Development (PUD) for three sites including CarMax,
Costco, and a proposed medical office building. Only the Costco development has been
constructedto date,in addition to grading, wetland mitigation, and stormwater system
improvements for the overall site. The City Council has approved several extensionsto
the CarMax projectand PUD conditions since then. Therefore, a majority of the PUD
conditions will still apply for CarMax’s updated proposal.
Tree Preservation Ordinance
A.:The City’s tree preservation ordinance was
adopted in 2006. The ordinance describes a significant tree as a hardwood tree
with a minimum of 6 inches in diameter, an evergreen tree with a minimum of 8
inches in diameter, and a softwood tree witha minimum of 12 inches in diameter.
The ordinance requires any significant tree removed to be replaced based on a
tree mitigation calculation.
Tree Removal and Required Replacement
:The Mogren Addition plat was
required to follow the City’s tree preservation guidelines. Based on a tree
inventory and tree removal plan submitted with the Mogren Addition plat in 2007,
the City required the following tree replacements for each site:
Caliper Inches Replacement Caliper
SiteRemoved InchesRequired
Costco 585702
523
Carmax436
Medical Office494593
Total
Removed1515
1
Attachment 10
Proposed Tree Replacement:
The applicant’s landscape plan shows a total of
161 replacement trees (including 111 – 2.5 caliper inch deciduous trees, 24
ornamental trees, and 31 8-foot high evergreen trees). This equals 404 caliper
inches of replacement trees, which does not meet the original PUDtree
replacement requirement of 523 caliper inches.
Tree replacement guidelines specify that a developer must install as many trees
as feasible on the site. After putting in as many trees as feasible, if the developer
still has not met the replacement requirements, mulched beds of native or
drought tolerant shrubs will qualify towards tree replacement. A #2 or #3 shrub
will be equivalent to .5 caliper inches. The rationale for allowing shrubs is that
mulched beds of hardy native shrubsrequire less fertilizer, pesticide, and water
than lawn.
The applicant’s landscape plan shows a total of 389 shrubs to be planted
throughout the site. This does not include the required rainwater garden
plantings on the north side of the site. This equals a total of 119 caliper inches of
replacement shrubs. If the City allows the inclusion of the shrubs, the applicant
will meet the tree replacementrequirements for a total of 523 caliper inches of
replacement trees.
City staff is not convinced that the applicant has installed as many trees as
feasible on the site. The applicant is proposing very large tree spacing along the
Highway 61 and Beam Avenue frontageswhere there is ample room to plant
additional trees.
Tree Preservation Recommendation
: The applicant must submit a revised
landscape plan showing an additional 119 caliper inches of trees to be planted
on the site. This can be accomplished by adding trees to the site or increasing
the size of the replacement trees.
Wetland Ordinance
B. :The wetland to the north of the site was constructed as
part of the Mogren Addition plat wetland mitigation requirements. The mitigated
wetland buffer requirements included the creation of up to 1.60 acres
(69,853square feet) of buffer, with an average buffer of 100 feet and a minimum
of 50 feet.The original CarMax development approved as part of the Mogren
Addition plat showed an average buffer of 100 feet and a minimum of 50 feet.
Additionally, the plans allowed for rainwater gardens to be constructed within the
buffer.
In 2007 the Ramsey-Washington Metro Watershed District reclassified all
wetlands within their district. The mitigated wetland is now classified as a
Manage A wetland. In 2009 the City adopted a new wetland ordinance which
requires the following for a Manage A wetland: 100-foot average buffer with a
minimum of 75 feetand stormwater ponds prohibited within a buffer. Regardless
of the City’s new wetland ordinance, the CarMax site is bound by the original
PUDwetland requirements of a 100-foot average and 50-foot minimum buffer.
Wetland Impacts:
The applicant’s grading, drainage, and erosion control plan
show the site developed to within 62 feet of the wetland edge on the north side of
the parking lot.The remainder of the developed site averages 100 feet. Grading
2
Attachment 10
will take place to within 5 or 10 feet of the wetland edge. This grading is needed
to construct the rainwater gardens which will be located between the parking lot
and the wetland.
The rainwater gardens will be constructed within the wetland buffer. The
applicant’s landscape plan shows that these gardens will be seeded with native
grass. Seeding infiltrationbasins is rarely successful since the seed is usually
washed away as water flows into the garden. As such, the City of Maplewood
requires that the rainwatergardens be planted, not seeded.Additionally, two of
the shrub plants shown in the plan are becoming invasive in our area – barberry
and miscanthus grass.
Wetland (Rainwater Garden Planting) Recommendations:
1.Submit a revised landscape plan for the rainwater gardens which
includes:
a.planting of native plants throughout the rainwater garden.If the
rainwatergardens exceed 5,000 square feet in total, seeding of
slopes could be permitted. However, because of the visibility to
the public the two gardens along Beam Avenue and Highway 61
should be planted.
b. replacement of the barberry and miscanthus grass with a
replacement species.
2.After grading and planting of the site the applicant must install city
approved wetland signs at the edge of the approved wetland buffer
(minimum of 50 feet to the wetland edge). The signs will specify that no
building, mowing, cutting, grading, filling or dumping be allowed within the
buffer. The signs must be placed every 100-feet along the edge.
3. The applicant must sign a wetland buffer restoration maintenance
agreement with the city which will require the applicant to ensure the
native plants are established within the buffer within a three-year period.
Shoreland Ordinance:
C.The southwest corner of the site (117,415 square feet)
is located within the Shoreland Overlay District of Kohlman Lake. Kohlman Lake
is a Class IV water. The City’s Shoreland Ordinance allows for a maximum of 30
percent impervious surface coverage for a lot located within this District, and up
to 50 percent impervious surface coverage with bonuses. The city engineer shall
determine whether bonuses are allowed based on the installation and
maintenance of manmade facilities for reducing stormwater flow or the treatment
of runoff for non-point-source water pollutants.
Impervious Surface Area:
The applicantproposes 26,683 square feet of
porous paving to comply with the pervious pavement requirements. With the
pervious pavement and minimal green space required with the parking lot
setback and landscaping adjacent the boulevard, the applicant’s site plan shows
57 percent (50,488 square feet) of impervious surface area within the Kohlman
Lake Shoreland District boundary.This is 7 percent over the allowable 50
percent impervious surface allowed with bonuses.
3
Attachment 10
Shoreland Recommendation:
The applicant must submit arevised plan which
shows an increase of 8,200 square feet of bituminous porous pavement in order
to maintain a maximum of 50 percent impervious surface coverage within the
Shoreland District.
4
Attachment 11
Attachment 11
Attachment 11
Attachment 12
MEMORANDUM
TO:Charles Ahl, City Manager
FROM:Michael Martin, AICP, Planner
Melinda Coleman, Assistant City Manager
DATE:September 18, 2013
Approval of a Resolution for a Comprehensive Plan Amendment,
SUBJECT:
Resolution for a Conditional Use Permit, Design Reviewand Parking
Waiver for Maplewood Fire Station No. 1,McKnight Road
A.Approval of a Resolution for a Comprehensive Plan
Amendment
B.Approval of Resolution for a Conditional Use Permit
C.Approval of Design Review
D.Approval of a Parking Waiver
Introduction
Project Description
The Maplewood Fire Department is proposing to build a 16,409-square-foot, one-story fire
station north of the new 3M Company research building.The fire station will be built on land
dedicated to the city by 3M Company. The facility will also include space for a police substation.
Requests
The applicant is requesting that the city council approve:
1.A comprehensive land use plan amendment from I(Industrial) to G (Government). The
code requires that, to approve a conditional use permit (CUP), the land use plan
designation for a property must be in conformance with the proposed use.
2.A CUP for a public building. The city code requires a CUP for “public utility, public
service or public building uses.”
3.Design plans, which include building, site and landscape plans.
4.A parking waiver to allow for fewer parking spaces than required by ordinance.
Background
June 28, 2013, city staff approved a minor lot division which divides the site for the proposed fire
stationfrom the rest of the 3M campus. This approval also creates a separate legal parcel for
the recently approved research building on the 3M campus.
Discussion
Comprehensive Plan Amendment
The city council must approve the proposed land use plan change to G if they wish to approve
the CUP. Staff recommends approval of this change since the proposed use complies with the
general development policies in the comprehensive plan. Public buildings are allowed in all
zoning districts so a zoning amendment is not required.
Conditional Use Permit
The proposed fire station would be compatible with this neighborhood.Staff surveyed property
owners within 500 foot of this site, both in Maplewood and Saint Paul, and did not receive any
responses.
Traffic
Traffic will increase, but a fire station is not a high traffic generating use. The proposed fire
station will, in fact, create much less traffic than if this land were developed as currently zoned
and planned.
Noise
Noise associated with the fire station would be the occasional fire call with siren and vehicle
noise associated with it.
Design Review
The proposed building would be attractive.The exterior of the building will include brick and
concrete masonry units designed to look like Kasota stone and surface mounted LED lighting. A
light colored, thermo-plastic polyolefin, low pitched roof system is designed to reflect heat and
control rainwater runoff to the rain gardens located on the site. LED site lighting will be provided
and controlled to minimize spill to adjacent properties.
The proposed site is elevated above 3M Lake, along McKnight Road, between a service road to
the south of Minnehaha Avenue and a service road into the 3M campus. The building will be
placed on the northwest corner of the site, which is elevated, treeless and provides access to the
north boundary service road and McKnight Road. The building layout and site will allow itself to
promote the use of rain gardens for control and filtration of runoff before entering 3M Lake.
Evergreens and ornamental trees will be provided on the west side of the building, providing a
screen from the residential use across McKnight Road.
Environmental Review
The site is near 3M Lake, which is also a Manage B wetland, which requires a 75-foot buffer.
The proposed building project will meet the wetland setback requirements from 3M Lake.
3M Lake is classified as aClass 1 Lake in the City’s shoreland ordinance.Buildings need to
maintain a 50 foot setback from a Class 1 Lake.Maximum impervious surface area is 50
percent.The site can have up to 70 percent impervious with approved best practices bonuses.
The entire site is within the Shoreland area.The site is 3.23 acres and the impervious coverage
is 2.20 acres or 68 percent.The city engineer has agreed to allow an 18 percent bonus for
impervious surface for the use of raingardens on site which will double the amount of stormwater
required to be collected on site.
No trees are to be removed during the building of this project, so therefore no additional trees
are required to be planted. The landscape plan does show 39 trees are to be planted.
Photometric Plan
The photometric plan submitted by the applicant displays the light intensities within the actual
project area, but not at all property lines. The applicant shall submit a revised photometric plan
showing compliance with the ordinance’s requirement of not exceeding 0.4 footcandles at the
north and west property lines.
Parking Waiver
The applicanthas proposed 19 visitor parking spaces tobe included on the north side of the fire
station as well as 4 employee parking spaces on the south side of the station.Code would
typically require 66parking spaces. The office area of the building totals 6,965.5 square feet
which requires 35 spaces. The apparatus bays and support areas total 9,443.5 square feet,
which required 31 spaces. This is not a facility that would expect to see a high number of
visitors. Staff is comfortable with approving a parking waiver of 43parking spaces.
Department Comments
Building Official’s Comments
The building will need to comply with the State Building Code.We are recommending that the
architect follows the City’s new Green Building Ordinance and we have about this as well.
Fire Marshall’s Comments
Will need to comply with all state and local fire codes concerning fire protection and fire alarm
systems.
City Engineer’s Comments
Michael Thompson, city engineer reviewed thisproposal and commented;“No commenthere.
The plan is consistent with ongoing coordination and discussions.”
Committee Review
September 24, 2013: The community design review board will review this project.
October 1, 2013: The planning commission will review this project.
Recommendations
A.Approve the plans, date-stamped September 11, 2013for the proposed Maplewood Fire
Station No. 1, based on the findings required by the code. The property owner shall do the
following:
1.Repeat this review in two years if the city has not issueda building permit for this project.
2.Submit a revised photometric plan showing compliance with code at all property lines.
3.Complete the following before occupying the building:
a.Install all landscaping as shown on the approved plan.
b.Screen any roof-topmechanical equipment that would be visible from the homes
along McKnight Road. All other roof-top units that are visible from non residential
areas must be painted to match the building.
c.Provide handicap-accessible parking spaces and signs as required by the ADA
(American’s with Disabilities Act).
4.All work shall follow the approved plans. The director of community development may
approve minor changes.
B.Approve a parking waiver to allow for 23 surface parking spaces. This is a parking reduction
of42parking spaces (66parking spaces are required per city code).
NeighborhoodSurvey
Staffsurveyed the 52property owners within 500feet of this site for their comments. Staff did
not receive any comments regarding this project.
Reference Information
Site Description
Site size:3.23acres
Existing land use:Undeveloped
Surrounding Land Uses
North:Wells Fargo
South:3M Company
West:McKnight Road and Single-Family Homes
East:3M Lake
Planning
Land Use Plan designation:Existing –I(Industrial); Proposed –G (Government)
Zoning: M1(Light Manufacturing)
Attachments
1.Location Map
2.Aerial Site Map
3.Land Use Map
4.Zoning Map
5.Site Plan
6.Landscape Plan
7.Building Elevations
8.Photometric Plan
9.Applicant’s Letters
10.Plans date-stamped September11, 2013(separate attachments)
P:\SEC36\MCKNIGHT_00_Firestation 1
Attachment 1
Fire
Station
3M Campus
Proposed Maplewood Fire Station
Location Map
Attachment 2
Wells Fargo
Fire
Station
3M Campus
Proposed Maplewood Fire Station
Aerial Site Map
Attachment 3
Wells Fargo
Fire
Station
(I) Industrial
3M Campus
Proposed Maplewood Fire Station
Future Land Use Map
Attachment 4
Wells Fargo
Fire
Station
(M1) Light Manufacturing
3M Campus
Proposed Maplewood Fire Station
Zoning Map
Attachment 6
Attachment 7
Attachment 7
Attachment 7
Attachment 8
Attachment 9
WRITTEN NARRATIVE
The project proposes to construct a new City of Maplewood Fire Station #1 at the northwest corner of
the 3M campus, near the intersection of McKnight Road and Minnehaha Avenue. The facility will be
comprised of 16,409 square feet of space to house four fire department apparatus bays, departmental
offices and staff support spaces. The facility will also include space for a police department substation.
The facility size, scope and plan were determined through planning work sessions with department staff
and consideration of the site and context of the 3M campus. The building will accommodate the city’s
fire department needs for the foreseeable future.
The exterior of the building will include brick and concrete masonry units designed to look like Kasota
stone and surface mounted LED lighting. A light colored, thermo-plastic polyolefin, low pitched roof
system is designed to reflect heat and control rainwater runoff to the rain gardens located on the site.
LED site lighting will be provided and controlled to minimize spill to adjacent properties.
The proposed site is elevated above 3M Lake, along McKnight Road, between a service road to the south
of Minnehaha Avenue and a service road into the 3M campus. The building will be placed on the
northwest corner of the site, which is elevated, treeless and provides access to the north boundary
service road and McKnight Road. The building layout and site will allow itself to promote the use of rain
gardens for control and filtration of runoff before entering 3M Lake. Evergreens and ornamental trees
will be provided on the west side of the building, providing a screen from the residential use across
McKnight Road. Native trees, shrubs, perennials and seed mixes will be provided around the remaining
portions of the site to provide positive growth year after year while also providing minimal
maintenance. 19 visitor parking spaces will be included on the north side of the fire station as well as 4
employee parking spaces on the south side of the station. Flashing beacons controlled with an
emergency vehicle preemption device will be placed at the McKnight Road exit to warn motorists that
fire trucks are leaving the premises.
It is anticipated construction will begin in March 2014 and continue until November 2014.
Approval of a Conditional Use Permit for this project will not result in any adverse traffic or
environmental impacts to the surrounding area.
Attachment 9
Filing Requirement 1.b Narrative:
A variance is requested for the required number of parking spaces for the City of Maplewood Fire Station
No. 1 project. The project includes a four stall, drive thru apparatus bay with a support space and a
storage mezzanine and fire department support space consisting of offices, a conference/training room,
dormitory space, an exercise room, kitchen and dayroom. A police department substation is also included
within the proposed fire station building.
The City’s Zoning Code has been reviewed regarding parking requirements. The office area of the
building totals 6,965.5 gross square feet requiring 35 parking stalls by Ordinance. The apparatus bay and
support area totals 9,443.5 gross square feet requiring an additional 31 parking stalls. The number of stalls
required by City Ordinance for the entire building is 66. We are requesting a variance in the parking
requirements to reduce this number to 23 stalls. The station will be occupied by a maximum of five fire
fighters and one police officer at any given time and does not contain spaces that will be open for public
use. The 23 stalls requested will provide more than an adequate number of spaces for the rare occasion